229-231 W 99TH ST 90003
Certificate Information: 229-231 W 99TH ST 90003
- Application / Permit
- 21010-10000-01417
- Plan Check / Job No.
- B21LA05491
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-STORY DUPLEX WITH 3-CAR ATTACHED GARAGE
- Permit Issued
- Issued on 8/27/2021
- Issuing Office
- Current Status
- CofO Issued on 1/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | DANIEL YIP |
| Corrections Issued | 4/5/2021 | DANIEL YIP |
| Quality Review Completed | 4/12/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 4/15/2021 | APPLICANT |
| Plan Check Approved | 7/13/2021 | DANIEL YIP |
| Issued | 8/27/2021 | APPLICANT |
| CofO in Progress | 1/6/2022 | EUGENE CASSIDY |
| Permit Finaled | 1/10/2022 | DEROLD HAUFF |
| CofO Issued | 1/10/2022 | DEROLD HAUFF |
| Permit Finaled | 1/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 5/10/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 6/4/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/7/2021 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 7/1/2021 | RICHARD REASER |
| Sewer availability | Cleared | 7/2/2021 | JEANIE LAM |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 10/1/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 10/4/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 11/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 11/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 11/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 11/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 11/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 11/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 11/2/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/3/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/3/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 11/3/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 11/3/2021 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 11/3/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/3/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 11/3/2021 | Approved | EUGENE CASSIDY |
| Insulation | 11/4/2021 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 11/10/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/10/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/13/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/5/2022 | Approved | EUGENE CASSIDY |
| Final | 1/5/2022 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 1/5/2022 | Approved | EUGENE CASSIDY |
| HVAC-Final | 1/5/2022 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 1/5/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/5/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 1/5/2022 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 1/5/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 1/6/2022 | Approved | EUGENE CASSIDY |