2209 W RIDGEVIEW AVE 90041
Certificate Information: 2209 W RIDGEVIEW AVE 90041
- Application / Permit
- 21010-10000-01402
- Plan Check / Job No.
- B21LA05395
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY ADU PER LAMC 12.22 A33 C & D
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | STARR CHEN |
| Corrections Issued | 3/29/2021 | STARR CHEN |
| Plan Check Approved | 9/30/2021 | ADAM HEGAZI |
| Issued | 10/12/2021 | APPLICANT |
| Building Plans Picked Up | 10/14/2021 | APPLICANT |
| CofO in Progress | 9/28/2022 | CRAIG VAUGHAN |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | CELINA MORENO |
| Sewer availability | Cleared | 4/21/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 6/8/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 9/1/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 9/8/2021 | CELINA MORENO |
| GPI Written Notices | Cleared | 9/22/2021 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 9/22/2021 | STARR CHEN |
Contact Information
| Architect | Mojdehi,, Mariam; Lic. No.: C37992 | 3746 GRAYBURN AVE LOS ANGELES, CA 90018 |
| Contractor | Williams Christopher; Lic. No.: 711380-B | P O BOX 8652 LA CRESCENTA, CA 91224 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/15/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 12/15/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/27/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/14/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/16/2022 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 3/1/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Partial Approval | CRAIG VAUGHAN |
| Deputy Wood Construction | 5/3/2022 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/12/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/12/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 5/12/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 5/12/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/12/2022 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 5/12/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 5/25/2022 | Approved | SCOTT FINNILA |
| Insulation | 6/8/2022 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 6/16/2022 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 6/20/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/20/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/21/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Sewer | 8/3/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 8/3/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 8/8/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 9/15/2022 | Corrections Issued | SCOTT FINNILA |
| Final | 9/15/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 9/15/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 9/15/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 9/15/2022 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Not Ready | SCOTT FINNILA |
| Service/Power Release | 9/15/2022 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 9/15/2022 | Approved | SCOTT FINNILA |
| Pre-Inspection | 9/16/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Final | 9/27/2022 | Approved | CRAIG VAUGHAN |
| Final | 9/27/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| PLUMBING-Final | 9/27/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 9/27/2022 | Approved | CRAIG VAUGHAN |