2209 W RIDGEVIEW AVE 90041

Certificate Information: 2209 W RIDGEVIEW AVE 90041

Application / Permit
21010-10000-01402
Plan Check / Job No.
B21LA05395
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY ADU PER LAMC 12.22 A33 C & D
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 STARR CHEN
Corrections Issued 3/29/2021 STARR CHEN
Plan Check Approved 9/30/2021 ADAM HEGAZI
Issued 10/12/2021 APPLICANT
Building Plans Picked Up 10/14/2021 APPLICANT
CofO in Progress 9/28/2022 CRAIG VAUGHAN
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/19/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/21/2021 CELINA MORENO
Sewer availability Cleared 4/21/2021 CELINA MORENO
Hydrant and Access approval Cleared 6/8/2021 ROBERT DUFF
Low Impact Development Cleared 9/1/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 9/8/2021 CELINA MORENO
GPI Written Notices Cleared 9/22/2021 STARR CHEN
Grading Pre-Inspection Cleared 9/22/2021 STARR CHEN

Contact Information

Architect Mojdehi,, Mariam; Lic. No.: C37992 3746 GRAYBURN AVE      LOS ANGELES, CA 90018
Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/15/2021 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 12/15/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 12/27/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 1/14/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 2/16/2022 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/1/2022 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 5/3/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/12/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/12/2022 Approved CRAIG VAUGHAN
Green Building Rough 5/12/2022 Approved CRAIG VAUGHAN
HVAC-Rough 5/12/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 5/12/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/12/2022 Approved CRAIG VAUGHAN
HVAC-Rough 5/25/2022 Approved SCOTT FINNILA
Insulation 6/8/2022 Approved KATHRYN BUTTERWORTH
Underground Mechanical 6/16/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 6/20/2022 Approved AMY COLIN
Interior/Exterior Lathing 6/20/2022 Approved AMY COLIN
ELECTRICAL-Final 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 6/21/2022 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 6/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Sewer 8/3/2022 Approved CRAIG VAUGHAN
Underground Mechanical 8/3/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 8/8/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 9/15/2022 Corrections Issued SCOTT FINNILA
Final 9/15/2022 Corrections Issued SCOTT FINNILA
Green Building Final 9/15/2022 Approved SCOTT FINNILA
HVAC-Final 9/15/2022 Approved SCOTT FINNILA
PLUMBING-Final 9/15/2022 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 9/15/2022 Corrections Issued SCOTT FINNILA
Smoke Detectors 9/15/2022 Approved SCOTT FINNILA
Pre-Inspection 9/16/2022 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 9/27/2022 Approved CRAIG VAUGHAN
Final 9/27/2022 OK to Issue CofO CRAIG VAUGHAN
PLUMBING-Final 9/27/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 9/27/2022 Approved CRAIG VAUGHAN