851 1/2 E EL PASO DR 90042

Certificate Information: 851 1/2 E EL PASO DR 90042

Application / Permit
21010-10000-01386
Plan Check / Job No.
B21LA05372
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 9/1/2022
Issuing Office
Metro
Current Status
Issued on 9/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 DANIEL YIP
Corrections Issued 6/14/2021 DANIEL YIP
Quality Review Completed 6/22/2021 JASON HEALEY
Building Plans Picked Up 6/24/2021 APPLICANT
Applicant returned to address corrections 8/19/2021 DANIEL YIP
Applicant returned to address corrections 9/24/2021 DANIEL YIP
Applicant returned to address corrections 10/19/2021 DANIEL YIP
Applicant returned to address corrections 10/22/2021 DANIEL YIP
Applicant returned to address corrections 12/9/2021 DANIEL YIP
Plan Check Approved 7/18/2022 DANIEL YIP
Issued 9/1/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/21/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 7/21/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 7/21/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/21/2021 WALLIE JONG
Sewer availability Cleared 7/22/2021 WALLIE JONG
Miscellaneous Cleared 8/2/2021 RUBEN VASQUEZ
GPI Written Notices Cleared 10/19/2021 DANIEL YIP
Grading Pre-Inspection Cleared 10/19/2021 DANIEL YIP
Specific Plan Cleared 12/9/2021 NASHYA JENSEN
Street Frontage Cleared 12/15/2021 WALLIE JONG
Hydrant and Access approval Cleared 1/29/2022 JOHN CONNEALLY
Low Impact Development Cleared 6/23/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 9/1/2022 CINDY QI
Hold Cleared 12/30/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/6/2022 Corrections Issued OSVALDO PARAMO
Underground Mechanical 9/6/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 9/15/2022 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 1/3/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 1/3/2023 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 1/3/2023 Partial Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 1/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 1/3/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/12/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Approved OSVALDO PARAMO
Insulation 1/19/2023 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/25/2023 Approved JEFFREY MEAD
HVAC-Rough 1/25/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 2/2/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 2/7/2023 Approved OSVALDO PARAMO
Deputy Wood Construction 2/8/2023 Conditional Approval OSVALDO PARAMO
HVAC-Rough 2/14/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/9/2023 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Approved OSVALDO PARAMO
Green Building Rough 3/9/2023 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 3/9/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/20/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/20/2023 Partial Approval OSVALDO PARAMO
Insulation 3/28/2023 Approved OSVALDO PARAMO
Drywall Nailing 5/18/2023 Approved OSVALDO PARAMO
Sewer 7/19/2023 Approved OSVALDO PARAMO
Underground Mechanical 7/19/2023 Approved OSVALDO PARAMO
Final 1/2/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 1/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/2/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 1/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 1/2/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Not Ready BRIAN SULLIVAN
Final 6/2/2026 Corrections Issued OSVALDO PARAMO
Green Building Final 6/2/2026 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/2/2026 SGSOV Approved OSVALDO PARAMO
Service/Power Release 6/2/2026 Not Ready for Inspection OSVALDO PARAMO