921 1/2 E 54TH ST 90011

Certificate Information: 921 1/2 E 54TH ST 90011

Application / Permit
21010-10000-01384
Plan Check / Job No.
B21LA05358
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) Detached ADU (903 SF) per LAMC 12.22 A.33 (c), (d)
Permit Issued
Issued on 7/26/2022
Issuing Office
Current Status
CofO Issued on 8/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 AARON COSTA
Corrections Issued 3/25/2021 AARON COSTA
Building Plans Picked Up 4/9/2021 APPLICANT
Plan Check Approved 7/26/2022 ADAM HEGAZI
Issued 7/26/2022 APPLICANT
CofO in Progress 8/12/2025 ALEJANDRO DE ARTOLA
Permit Finaled 8/15/2025 DEROLD HAUFF
CofO Issued 8/15/2025 DEROLD HAUFF
Permit Finaled 8/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/20/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 4/21/2021 THOMAS LANG
Sewer availability Cleared 4/21/2021 THOMAS LANG
Hydrant and Access approval Cleared 1/26/2022 KURT CORRAL
Low Impact Development Cleared 5/23/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 5/26/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/19/2022 Corrections Issued JOAQUIN GREENOUGH
Piling/Pier/Caisson 8/19/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 8/26/2022 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/26/2022 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 9/13/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Rough 9/14/2022 Approved SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Partial Approval SHAVONNE ESPINOZA
Pre-Inspection 9/16/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 10/28/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 10/28/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 10/28/2022 Approved ALIZAH MAYAGOITIA
Wood Frame 10/28/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/18/2022 Corrections Issued ALIZAH MAYAGOITIA
Sewer 11/18/2022 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 12/20/2022 Conditional Approval BRENDAN MORELLI
Interior/Exterior Lathing 5/19/2023 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 7/6/2023 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 10/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 12/8/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/1/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 2/1/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 2/1/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 2/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 2/23/2024 Approved ALEJANDRO DE ARTOLA
Insulation 2/23/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 2/28/2024 Approved ENRIQUE MIRELES
Drywall Nailing 3/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 3/8/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/16/2024 Partial Approval AMY COLIN
Shower Pan 4/16/2024 Approved AMY COLIN
Interior/Exterior Lathing 4/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/3/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/18/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Final 9/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 10/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 10/10/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/10/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/16/2024 Approved ALEJANDRO DE ARTOLA
Green Building Final 12/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/16/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 12/16/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/20/2024 Approved ALEJANDRO DE ARTOLA
Final 12/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 12/20/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
HVAC-Final 12/27/2024 Not Ready for Inspection SABAS ALONSO
Final 12/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/30/2024 Approved ALEJANDRO DE ARTOLA
Final 8/11/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Approved ALEJANDRO DE ARTOLA