4237 N AGNES AVE 91604
Certificate Information: 4237 N AGNES AVE 91604
- Application / Permit
- 21010-10000-01333
- Plan Check / Job No.
- B21LA05138
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New 2-story Accessory Building. 2-car Attached Garage with Rec Room & Pool bathroom at 1st floor. Accessory Dwelling Unit at 2nd floor.
- Permit Issued
- Issued on 10/29/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | PRANITA SHAH |
| Corrections Issued | 5/20/2021 | PRANITA SHAH |
| Quality Review Completed | 5/25/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 7/28/2021 | PRANITA SHAH |
| Plan Check Approved | 10/26/2021 | PRANITA SHAH |
| Issued | 10/29/2021 | APPLICANT |
| CofO in Progress | 7/19/2023 | JACK KARGODORIAN |
| Permit Finaled | 8/17/2023 | RUBEN SALAS |
| CofO Issued | 8/17/2023 | RUBEN SALAS |
| Permit Finaled | 8/17/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/9/2021 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 6/18/2021 | RIDWAN HARDY |
| ZI | Cleared | 6/24/2021 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 8/31/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 10/5/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/6/2021 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Nichols,, Mark; Lic. No.: NA38099 | , |
| Contractor | Crescent Canyon Corp; Lic. No.: 1023601-B | , |
| Engineer | Harris,, William Donald; Lic. No.: NA5121 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/9/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/30/2022 | Partial Approval | MATT KELLERMAN |
| Underground Mechanical | 3/30/2022 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Rough | 4/11/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/18/2022 | Approved | THOMAS FINNILA |
| Sewer | 5/9/2022 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 5/9/2022 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 5/19/2022 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 5/19/2022 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/15/2022 | Partial Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/16/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 9/19/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 9/19/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/13/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 10/13/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 10/14/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 10/18/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 11/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/8/2022 | Partial Approval | JACK KARGODORIAN |
| Insulation | 1/4/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 1/17/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/17/2023 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 1/17/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/20/2023 | Partial Approval | JACK KARGODORIAN |
| Final | 6/27/2023 | OK to Issue CofO | JOHN COLEMAN |
| Green Building Final | 6/27/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 6/27/2023 | Approved | JOHN COLEMAN |
| Smoke Detectors | 6/27/2023 | Approved | JOHN COLEMAN |