332 S SALTAIR AVE 90049

Certificate Information: 332 S SALTAIR AVE 90049

Application / Permit
21010-10000-01318
Plan Check / Job No.
B21LA05100
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 1-CAR GARAGE
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 DANIEL YIP
Corrections Issued 4/29/2021 DANIEL YIP
Quality Review Completed 5/12/2021 JASON HEALEY
Building Plans Picked Up 5/14/2021 APPLICANT
Applicant returned to address corrections 6/25/2021 DANIEL YIP
Applicant returned to address corrections 9/8/2021 DANIEL YIP
Plan Check Approved 9/17/2021 DANIEL YIP
Issued 9/27/2021 APPLICANT
CofO in Progress 9/2/2023 CARLOS MATAMOROS
Permit Finaled 9/12/2023 DANIEL ORRANTE
CofO Issued 9/12/2023 DANIEL ORRANTE
Permit Finaled 9/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 4/29/2021 DANIEL YIP
Grading Pre-Inspection Cleared 4/29/2021 DANIEL YIP
Eng Process Fee Ord 176,300 Cleared 6/14/2021 DINAH GARIN
Sewer availability Cleared 6/14/2021 DINAH GARIN
Address approval Cleared 6/17/2021 DINAH GARIN
Specific Plan Cleared 7/27/2021 PETE EYRE
Low Impact Development Cleared 8/5/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 8/9/2021 SAUL GARCIA
Trees in Parkway Cleared 8/10/2021 JOHN KIM
Hydrant and Access approval Cleared 8/22/2021 JOHN CONNEALLY
Disturb/Remove Protected Trees Cleared 8/31/2021 STEPHEN DUPREY

Contact Information

Architect Wolen,, Deborah Suzanne; Lic. No.: C29672 P O BOX 352011      LOS ANGELES, CA 90035
Contractor G P G Inc; Lic. No.: 714663-B 4924 BALBOA BLVD STE 610      ENCINO, CA 91316
Engineer Yates,, Gerald Lee; Lic. No.: C73972 6309 DEL AMO BLVD      LAKEWOOD, CA 90713

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/10/2022 Corrections Issued JOHN KIDWELL
Deputy Reinf. Concrete 1/13/2022 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/19/2022 Partial Inspection MICHAEL PELHAM
PLUMBING-Rough 1/19/2022 Partial Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 1/27/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 1/28/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 2/15/2022 Partial Approval JOHN KIDWELL
Special/Order Compliance 4/8/2022 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 4/21/2022 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 4/21/2022 Corrections Issued JOHN KIDWELL
Sewer 8/4/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 9/1/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 9/1/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 10/24/2022 Approved KEVIN SARGSYAN
Underground Mechanical 10/24/2022 Approved KEVIN SARGSYAN
HVAC-Rough 11/22/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 12/8/2022 Partial Approval DAVID FEILER
Green Building Rough 12/8/2022 Not Ready for Inspection DAVID FEILER
Final 12/9/2022 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 12/20/2022 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 12/27/2022 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 1/3/2023 Approved KEVIN SARGSYAN
Green Building Rough 1/3/2023 Approved KEVIN SARGSYAN
Insulation 1/3/2023 Approved KEVIN SARGSYAN
Shower Pan 1/3/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 1/13/2023 Approved KEVIN SARGSYAN
Drywall Nailing 2/7/2023 Partial Approval OGANES TARAKHCHYAN
Pre-Inspection 5/16/2023 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 5/26/2023 Approved OGANES TARAKHCHYAN
Service/Power Release 5/26/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 6/23/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Final 6/23/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 8/7/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 8/22/2023 Approved OGANES TARAKHCHYAN
Gas Test 8/29/2023 Approved KEVIN SARGSYAN
Drywall Nailing 9/1/2023 Approved CARLOS MATAMOROS
Final 9/1/2023 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 9/1/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/1/2023 Approved CARLOS MATAMOROS