332 S SALTAIR AVE 90049
Certificate Information: 332 S SALTAIR AVE 90049
- Application / Permit
- 21010-10000-01318
- Plan Check / Job No.
- B21LA05100
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 1-CAR GARAGE
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 9/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | DANIEL YIP |
| Corrections Issued | 4/29/2021 | DANIEL YIP |
| Quality Review Completed | 5/12/2021 | JASON HEALEY |
| Building Plans Picked Up | 5/14/2021 | APPLICANT |
| Applicant returned to address corrections | 6/25/2021 | DANIEL YIP |
| Applicant returned to address corrections | 9/8/2021 | DANIEL YIP |
| Plan Check Approved | 9/17/2021 | DANIEL YIP |
| Issued | 9/27/2021 | APPLICANT |
| CofO in Progress | 9/2/2023 | CARLOS MATAMOROS |
| Permit Finaled | 9/12/2023 | DANIEL ORRANTE |
| CofO Issued | 9/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/29/2021 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 4/29/2021 | DANIEL YIP |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | DINAH GARIN |
| Sewer availability | Cleared | 6/14/2021 | DINAH GARIN |
| Address approval | Cleared | 6/17/2021 | DINAH GARIN |
| Specific Plan | Cleared | 7/27/2021 | PETE EYRE |
| Low Impact Development | Cleared | 8/5/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/9/2021 | SAUL GARCIA |
| Trees in Parkway | Cleared | 8/10/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 8/22/2021 | JOHN CONNEALLY |
| Disturb/Remove Protected Trees | Cleared | 8/31/2021 | STEPHEN DUPREY |
Contact Information
| Architect | Wolen,, Deborah Suzanne; Lic. No.: C29672 | P O BOX 352011 LOS ANGELES, CA 90035 |
| Contractor | G P G Inc; Lic. No.: 714663-B | 4924 BALBOA BLVD STE 610 ENCINO, CA 91316 |
| Engineer | Yates,, Gerald Lee; Lic. No.: C73972 | 6309 DEL AMO BLVD LAKEWOOD, CA 90713 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/10/2022 | Corrections Issued | JOHN KIDWELL |
| Deputy Reinf. Concrete | 1/13/2022 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 1/19/2022 | Partial Inspection | MICHAEL PELHAM |
| PLUMBING-Rough | 1/19/2022 | Partial Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 1/27/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 1/28/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/15/2022 | Partial Approval | JOHN KIDWELL |
| Special/Order Compliance | 4/8/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/21/2022 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 4/21/2022 | Corrections Issued | JOHN KIDWELL |
| Sewer | 8/4/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 9/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/24/2022 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 10/24/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/22/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/8/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 12/8/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 12/9/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 12/20/2022 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/27/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/3/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 1/3/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 1/3/2023 | Approved | KEVIN SARGSYAN |
| Shower Pan | 1/3/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/13/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 2/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/16/2023 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 5/26/2023 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 5/26/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 6/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Final | 6/23/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 8/7/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 8/22/2023 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 8/29/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 9/1/2023 | Approved | CARLOS MATAMOROS |
| Final | 9/1/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 9/1/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/1/2023 | Approved | CARLOS MATAMOROS |