8112 S BARNSLEY AVE 90045
Certificate Information: 8112 S BARNSLEY AVE 90045
- Application / Permit
- 21010-10000-01301
- Plan Check / Job No.
- B21LA05062
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY 34'-7" X 36'-10" IRREG.-SHAPED A.D.U. PER ORDINANCE AT REAR OF LOT.
- Permit Issued
- Issued on 9/8/2021
- Issuing Office
- Current Status
- CofO Issued on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/25/2021 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/30/2021 | APPLICANT |
| Applicant returned to address corrections | 5/13/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 8/17/2021 | SHANGQIN XIE |
| Plan Check Approved | 9/7/2021 | LAWRENCE QUIRANTE |
| Issued | 9/8/2021 | APPLICANT |
| CofO in Progress | 9/16/2022 | BOBBY KEY |
| No Progress | 9/17/2022 | RICHARD STEINBACH |
| CofO in Progress | 9/19/2022 | BOBBY KEY |
| CofO in Progress | 10/19/2022 | RICHARD STEINBACH |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
| CofO Issued | 10/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/8/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 4/30/2021 | BRIAN MILLER |
| Low Impact Development | Cleared | 6/29/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/1/2021 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 8/5/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 8/6/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Ameera Enterprises Inc; Lic. No.: 935432-B | P O BOX 1331 HAWTHORNE, CA 90251 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/16/2021 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 9/22/2021 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 9/27/2021 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Partial Approval | DAVID FEILER |
| Sewer | 11/1/2021 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2021 | Approved | DAVID FEILER |
| Sewer | 11/5/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 11/5/2021 | Partial Approval | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 12/7/2021 | Partial Approval | BOBBY KEY |
| Wood Frame | 12/10/2021 | Approved | JOHN KAYON |
| Insulation | 12/14/2021 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 12/14/2021 | Approved | BOBBY KEY |
| Drywall Nailing | 12/21/2021 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 12/21/2021 | Approved | BOBBY KEY |
| Drywall Nailing | 1/10/2022 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/10/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | BOBBY KEY |
| Final | 6/3/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 6/3/2022 | Approved | BOBBY KEY |
| Green Building Final | 6/3/2022 | Approved | BOBBY KEY |
| Green Building Rough | 6/3/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 6/3/2022 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 6/3/2022 | Not Ready for Inspection | BOBBY KEY |
| Verify Sprinkler Sign Off | 6/3/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/23/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 6/24/2022 | Approved | BOBBY KEY |
| Service/Power Release | 6/24/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/13/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 7/28/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/28/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Approved | BOBBY KEY |
| Final | 9/16/2022 | Not Ready for Inspection | BOBBY KEY |
| Smoke Detectors | 9/16/2022 | Approved | BOBBY KEY |
| Final | 9/19/2022 | Corrections Issued | BOBBY KEY |
| Final | 10/19/2022 | OK to Issue CofO | RICHARD STEINBACH |