5142 N MONTE BONITO DR 90041
Certificate Information: 5142 N MONTE BONITO DR 90041
- Application / Permit
- 21010-10000-01280
- Plan Check / Job No.
- B21LA04936
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (45' X 19') 792 SF ONE STORY ADU PER CA GC 65852.2(e)(1)(B) AND LAMC 12.22.A.33(c)-(d), (g). SOLAR DEFFERED, SOLAR INSTALLATION REQUIRED, MIN. 1.65 KW REQUIRED PER TITLE 24, BEFORE C OF O. 1 OF 3
- Permit Issued
- Issued on 2/9/2022
- Issuing Office
- Current Status
- Issued on 2/9/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | VIVIAN LAO |
| Corrections Issued | 4/23/2021 | VIVIAN LAO |
| Quality Review Completed | 4/29/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 5/3/2021 | APPLICANT |
| Applicant returned to address corrections | 11/23/2021 | VIVIAN LAO |
| Plan Check Approved | 2/9/2022 | VIVIAN LAO |
| Issued | 2/9/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/18/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 10/6/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 10/29/2021 | GILBERT URREA |
| Hold | Cleared | 3/16/2022 | JASON SHEETS |
Contact Information
| Contractor | Eagle Rock Restoration; Lic. No.: 1025285-B | 5464 WAMEDA AVE LOS ANGELES, CA 90041 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/21/2022 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 4/27/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/11/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 6/2/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 10/3/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/3/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 10/3/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/14/2022 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 10/14/2022 | Partial Approval | CRAIG VAUGHAN |
| MERV13>=Rough | 10/14/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 10/31/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 1/20/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 2/10/2023 | Partial Approval | BRIAN SULLIVAN |
| Service/Power Release | 6/3/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | LILIANA PORTILLO |
| Final | 4/28/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 4/28/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| MERV13>=Final | 4/28/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 4/28/2025 | Approved | LILIANA PORTILLO |