1242 1/2 E ADAMS BLVD 90011

Certificate Information: 1242 1/2 E ADAMS BLVD 90011

Application / Permit
21010-10000-01278
Plan Check / Job No.
B21LA04921
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c)-(d)
Permit Issued
Issued on 8/1/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 DANIEL YIP
Corrections Issued 3/31/2021 DANIEL YIP
Quality Review Completed 4/3/2021 HERNAN ARREOLA
Applicant returned to address corrections 4/3/2021 HERNAN ARREOLA
Building Plans Picked Up 4/15/2021 APPLICANT
Applicant returned to address corrections 3/31/2023 DANIEL YIP
Plan Check Approved 8/1/2023 DANIEL YIP
Issued 8/1/2023 APPLICANT
CofO in Progress 12/23/2025 ALEJANDRO DE ARTOLA
Permit Finaled 12/28/2025 DEROLD HAUFF
Permit Finaled 12/28/2025 DEROLD HAUFF
CofO Issued 12/28/2025 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/20/2021 RICARDO BOHORQUEZ
Address approval Cleared 5/26/2021 RENZ SORIANO
Sewer availability Cleared 6/1/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/23/2021 RENZ SORIANO
Hydrant and Access approval Cleared 10/3/2021 KURT CORRAL
Low Impact Development Cleared 7/13/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/25/2023 ADRIAN SANCHEZ

Contact Information

Contractor Jou Mohamad Reza Jamshid; Lic. No.: 1102812-B 14655 VANOWEN STREET   UNIT A    VAN NUYS, CA 91405
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/15/2023 Partial Approval ALEJANDRO DE ARTOLA
Sewer 8/15/2023 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/7/2023 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/7/2023 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 9/11/2023 Approved ALEJANDRO DE ARTOLA
Deputy Steel/Welding 9/20/2023 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 10/13/2023 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 10/16/2023 Conditional Approval SCOTT FINNILA
Deputy Drilled-In Anchors 10/24/2023 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 12/28/2023 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 1/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 1/19/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/19/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/24/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 1/24/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/24/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/7/2024 Approved RONNIE MINDANAO
Green Building Rough 2/7/2024 Approved RONNIE MINDANAO
Insulation 2/7/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 2/7/2024 Approved RONNIE MINDANAO
Drywall Nailing 2/14/2024 Approved ALEJANDRO DE ARTOLA
Shower Pan 2/14/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/29/2024 Approved JOSH MEISTER
Gas Test 6/6/2025 Approved ANTHONY RAMOS
Underground Mechanical 6/6/2025 Approved ANTHONY RAMOS
Gas Test 9/16/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 9/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/3/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/3/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/19/2025 Approved ALEJANDRO DE ARTOLA
Final 12/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 12/19/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/19/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/19/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/19/2025 Approved ALEJANDRO DE ARTOLA
Final 12/23/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 12/23/2025 Approved ALEJANDRO DE ARTOLA