129-131 E 93RD ST 90003
Certificate Information: 129-131 E 93RD ST 90003
- Application / Permit
- 21010-10000-01277
- Plan Check / Job No.
- B21LA04920
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 1/13/2022
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | YOUNG KIM |
| Corrections Issued | 5/26/2021 | YOUNG KIM |
| Quality Review Completed | 6/1/2021 | SAI KHUM |
| Building Plans Picked Up | 6/9/2021 | APPLICANT |
| Applicant returned to address corrections | 9/22/2021 | YOUNG KIM |
| Applicant returned to address corrections | 11/24/2021 | YOUNG KIM |
| Applicant returned to address corrections | 1/6/2022 | YOUNG KIM |
| Applicant returned to address corrections | 1/11/2022 | YOUNG KIM |
| Plan Check Approved | 1/13/2022 | YOUNG KIM |
| Issued | 1/13/2022 | APPLICANT |
| CofO in Progress | 8/8/2022 | LILIANA PORTILLO |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2021 | STEVE MELGAR |
| Permit | Cleared | 6/21/2021 | STEVE MELGAR |
| Trees in Parkway | Cleared | 7/21/2021 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 7/22/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 8/30/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 9/9/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | STEVE MELGAR |
Contact Information
| Contractor | New World Construction; Lic. No.: 864461-B | 838 E 93RD STREET LOS ANGELES, CA 90002 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/1/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/1/2022 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 2/7/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/8/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 3/23/2022 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/5/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/6/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 4/11/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/11/2022 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 4/18/2022 | Approved | LILIANA PORTILLO |
| Final | 7/11/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 7/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/27/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/2/2022 | Approved | LILIANA PORTILLO |
| Final | 8/2/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Gas Test | 8/2/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 8/2/2022 | Approved | LILIANA PORTILLO |
| Final | 8/5/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 8/5/2022 | Approved | LILIANA PORTILLO |