915 1/2 E 105TH ST 90002
Certificate Information: 915 1/2 E 105TH ST 90002
- Application / Permit
- 21010-10000-01269
- Plan Check / Job No.
- B21LA04881
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW 20' x 23' DET. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2021 | SINA KHOSRAVI |
| Corrections Issued | 5/24/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/19/2021 | ZAW HAN |
| Building Plans Picked Up | 1/4/2022 | APPLICANT |
| Applicant returned to address corrections | 8/30/2022 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 2/16/2023 | RAMA DABADGE |
| Applicant returned to address corrections | 2/17/2023 | ISIS ARGUETA |
| Plan Check Approved | 2/21/2023 | ANGELICA MARTINEZ |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 4/25/2024 | ANSON MAGLASANG |
| CofO Issued | 4/25/2024 | ANSON MAGLASANG |
| Permit Finaled | 4/25/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2021 | STEVE MELGAR |
| Low Impact Development | Cleared | 1/27/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/3/2023 | CINDY QI |
| Sewer availability | Cleared | 2/15/2023 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/12/2023 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 6/27/2023 | Approved | JOHN KLARIN |
| Insulation | 7/19/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 7/25/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 7/25/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 8/1/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 8/18/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/3/2024 | Approved | JOHN KLARIN |
| Final | 1/3/2024 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 1/3/2024 | Approved | JOHN KLARIN |
| Green Building Final | 1/3/2024 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 1/3/2024 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 1/3/2024 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 1/3/2024 | Approved | JOHN KLARIN |
| Final | 1/24/2024 | No Access for Inspection | JAMES CHAVEZ |
| Green Building Final | 1/24/2024 | No Access for Inspection | JAMES CHAVEZ |
| Service/Power Release | 1/24/2024 | No Access for Inspection | JAMES CHAVEZ |
| Final | 1/30/2024 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 1/30/2024 | Approved | JOHN KLARIN |
| Service/Power Release | 1/30/2024 | Not Required | JOHN KLARIN |
| Final | 3/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 4/4/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 4/12/2024 | OK to Issue CofO | BEN MOLSTAD |