16722 W HORACE ST 91344

Certificate Information: 16722 W HORACE ST 91344

Application / Permit
21010-10000-01232
Plan Check / Job No.
B21LA04759
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU addition. 1 STORY ADU ADDITION TO EXISTING GARAGE. PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 8/23/2022
Issuing Office
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 CRYSTEL MAALOUF
Corrections Issued 4/19/2021 CRYSTEL MAALOUF
Quality Review Completed 4/26/2021 WING SUEN
Applicant returned to address corrections 3/21/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 6/13/2022 CRYSTEL MAALOUF
Plan Check Approved 6/22/2022 CRYSTEL MAALOUF
Issued 8/23/2022 APPLICANT
CofO in Progress 4/19/2023 JAVIER RAMOS JR
CofO Issued 4/26/2023 MICHAEL SMITH
Permit Finaled 4/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/28/2021 MATTHEW CRAIG
Construction near power lines Cleared 7/1/2021 RIDWAN HARDY
Construction within easement Cleared 7/1/2021 RIDWAN HARDY
Address approval Cleared 1/5/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/5/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/5/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 6/7/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/13/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer George,, John Lubenov; Lic. No.: C77289 10958 RUBIO AVE      GRANADA HILLS, CA 91344

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/15/2022 Approved JAVIER RAMOS JR
Sewer 11/15/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 12/7/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 12/23/2022 Approved JAVIER RAMOS JR
HVAC-Rough 12/23/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/23/2022 Approved JAVIER RAMOS JR
Underground Mechanical 12/23/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/5/2023 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 1/5/2023 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 1/5/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/9/2023 Partial Approval JAVIER RAMOS JR
Green Building Rough 1/9/2023 Approved JAVIER RAMOS JR
Insulation 1/9/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 1/19/2023 Approved JAVIER RAMOS JR
Drywall Nailing 1/19/2023 Approved JAVIER RAMOS JR
Insulation 1/19/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/25/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/28/2023 Approved JAVIER RAMOS JR
Final 3/28/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/28/2023 Approved JAVIER RAMOS JR
HVAC-Final 3/28/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 3/28/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 3/28/2023 Approved JAVIER RAMOS JR
Final 4/4/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 4/18/2023 OK to Issue CofO JAVIER RAMOS JR