5118 N STROHM AVE 91601
Certificate Information: 5118 N STROHM AVE 91601
- Application / Permit
- 21010-10000-01229
- Plan Check / Job No.
- B21LA04756
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan new ADU. New detached ADU 1,200 sf. 3 bedroom and 2 bathroom.
- Permit Issued
- Issued on 1/14/2022
- Issuing Office
- Current Status
- CofO Issued on 8/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 4/19/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/26/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 11/13/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/6/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/11/2022 | ARSALAN SHABESTARI |
| No Progress | 1/11/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/13/2022 | ARSALAN SHABESTARI |
| Issued | 1/14/2022 | APPLICANT |
| CofO in Progress | 7/26/2022 | JOHN HAYES |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
| CofO Issued | 8/24/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/11/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 8/17/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 10/14/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/11/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Genesis One Design & Development Co; Lic. No.: 984625-B | 1708 CAMINO LA VISTA FULLERTON, CA 92833 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/20/2022 | Approved | MATT KELLERMAN |
| Footing/Foundation/Slab | 1/20/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/20/2022 | Partial Approval | MISAEL ESPARZA |
| Pre-Inspection | 1/20/2022 | Approved | MATT KELLERMAN |
| Sewer | 1/20/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/7/2022 | Corrections Issued | MATT KELLERMAN |
| ELECTRICAL-Rough | 3/7/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Partial Approval | MATT KELLERMAN |
| Green Building Rough | 3/7/2022 | Not Ready for Inspection | MATT KELLERMAN |
| HVAC-Rough | 3/7/2022 | Corrections Issued | MATT KELLERMAN |
| PLUMBING-Rough | 3/7/2022 | Approved | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 3/7/2022 | Approved | MATT KELLERMAN |
| Wood Frame | 3/7/2022 | Partial Approval | MATT KELLERMAN |
| BUILDING-Rough-Frame | 3/11/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/11/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/11/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 3/11/2022 | Approved | JACK KARGODORIAN |
| Insulation | 3/25/2022 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 3/25/2022 | Partial Approval | CALEB MEISTER |
| Insulation | 3/30/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 3/30/2022 | Not Ready for Inspection | CALEB MEISTER |
| Shower Pan | 3/30/2022 | Corrections Issued | CALEB MEISTER |
| Drywall Nailing | 4/5/2022 | Approved | JACK KARGODORIAN |
| Shower Pan | 4/5/2022 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 4/12/2022 | Approved | CALEB MEISTER |
| Gas Test | 6/8/2022 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 6/8/2022 | Corrections Issued | ARAM AVEDISIAN |
| Underground Mechanical | 6/8/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 7/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/1/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 7/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 7/1/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 7/1/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 7/1/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 7/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 7/1/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/12/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 7/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/19/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Final | 7/26/2022 | Approved | JOHN HAYES |
| Final | 7/26/2022 | OK to Issue CofO | JOHN HAYES |
| Footing/Foundation/Slab | 7/26/2022 | Approved | JOHN HAYES |
| Green Building Final | 7/26/2022 | Approved | JOHN HAYES |
| PLUMBING-Final | 7/26/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 7/26/2022 | Approved | JOHN HAYES |
| Smoke Detectors | 7/26/2022 | Approved | JOHN HAYES |