4169 S DALTON AVE 90062

Certificate Information: 4169 S DALTON AVE 90062

Application / Permit
21010-10000-01208
Plan Check / Job No.
B21LA04609
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ADU [41 x 24] 2 bedrooms and 2 bathrooms.
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
CofO Issued on 4/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/22/2021 JESSE JIMENEZ
Corrections Issued 3/23/2021 JESSE JIMENEZ
Applicant returned to address corrections 10/28/2021 JESSE JIMENEZ
Plan Check Approved 2/16/2022 JAD BASMA
Issued 2/17/2022 APPLICANT
Building Plans Picked Up 2/22/2022 APPLICANT
CofO in Progress 4/10/2023 SABAS ALONSO
CofO Issued 4/15/2023 DEROLD HAUFF
Permit Finaled 4/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/7/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/8/2021 JEANIE LAM
Sewer availability Cleared 4/8/2021 JEANIE LAM
Construction near power lines Cleared 5/21/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 5/27/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/20/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 11/9/2021 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/7/2022 Corrections Issued SABAS ALONSO
Underground Mechanical 4/7/2022 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 4/18/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 4/18/2022 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 5/31/2022 Approved HORACE FULTZ
HVAC-Rough 5/31/2022 Approved HORACE FULTZ
PLUMBING-Rough 5/31/2022 Approved HORACE FULTZ
Wood Frame 5/31/2022 Approved HORACE FULTZ
Insulation 6/17/2022 Corrections Issued SABAS ALONSO
Insulation 6/20/2022 Approved SABAS ALONSO
Drywall Nailing 6/28/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 6/28/2022 Partial Approval SABAS ALONSO
Shower Pan 6/28/2022 Corrections Issued SABAS ALONSO
Shower Pan 7/5/2022 Corrections Issued SABAS ALONSO
Shower Pan 7/12/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 12/19/2022 Approved SABAS ALONSO
Final 12/19/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 12/19/2022 Approved SABAS ALONSO
Green Building Final 12/19/2022 Approved SABAS ALONSO
Green Building Rough 12/19/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Not Ready SABAS ALONSO
Service/Power Release 12/19/2022 Not Required SABAS ALONSO
Smoke Detectors 12/19/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 12/19/2022 Approved SABAS ALONSO
Final 1/5/2023 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/5/2023 SGSOV Approved SABAS ALONSO
Final 4/6/2023 Conditional Approval SABAS ALONSO
Final 4/10/2023 OK to Issue CofO SABAS ALONSO