4169 S DALTON AVE 90062
Certificate Information: 4169 S DALTON AVE 90062
- Application / Permit
- 21010-10000-01208
- Plan Check / Job No.
- B21LA04609
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ADU [41 x 24] 2 bedrooms and 2 bathrooms.
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- CofO Issued on 4/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2021 | JESSE JIMENEZ |
| Corrections Issued | 3/23/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 10/28/2021 | JESSE JIMENEZ |
| Plan Check Approved | 2/16/2022 | JAD BASMA |
| Issued | 2/17/2022 | APPLICANT |
| Building Plans Picked Up | 2/22/2022 | APPLICANT |
| CofO in Progress | 4/10/2023 | SABAS ALONSO |
| CofO Issued | 4/15/2023 | DEROLD HAUFF |
| Permit Finaled | 4/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/8/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 5/21/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 5/27/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/20/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/9/2021 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/7/2022 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 4/7/2022 | Conditional Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 4/18/2022 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 5/31/2022 | Approved | HORACE FULTZ |
| HVAC-Rough | 5/31/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 5/31/2022 | Approved | HORACE FULTZ |
| Wood Frame | 5/31/2022 | Approved | HORACE FULTZ |
| Insulation | 6/17/2022 | Corrections Issued | SABAS ALONSO |
| Insulation | 6/20/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/28/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/28/2022 | Partial Approval | SABAS ALONSO |
| Shower Pan | 6/28/2022 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 7/5/2022 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 7/12/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 12/19/2022 | Approved | SABAS ALONSO |
| Final | 12/19/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 12/19/2022 | Approved | SABAS ALONSO |
| Green Building Final | 12/19/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 12/19/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 12/19/2022 | Not Required | SABAS ALONSO |
| Smoke Detectors | 12/19/2022 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 12/19/2022 | Approved | SABAS ALONSO |
| Final | 1/5/2023 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Approved | SABAS ALONSO |
| Final | 4/6/2023 | Conditional Approval | SABAS ALONSO |
| Final | 4/10/2023 | OK to Issue CofO | SABAS ALONSO |