721-723 E 41ST PL 90011

Certificate Information: 721-723 E 41ST PL 90011

Application / Permit
21010-10000-01198
Plan Check / Job No.
B21LA04564
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR PER ENGINEER DESIGN (NFPA 13D THRU OUT)
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 AUNG SOE
Corrections Issued 3/23/2021 AUNG SOE
Quality Review Completed 3/24/2021 EUGENE BARBEAU
Building Plans Picked Up 3/30/2021 APPLICANT
Plan Check Approved 6/1/2021 AUNG SOE
Plan Check Approved 6/22/2021 AUNG SOE
Issued 6/25/2021 APPLICANT
CofO in Progress 1/20/2022 JOAQUIN GREENOUGH
Permit Finaled 1/29/2022 DEROLD HAUFF
CofO Issued 1/29/2022 DEROLD HAUFF
Permit Finaled 1/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/8/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/9/2021 CECILIO NAVARRO
Permit Cleared 4/13/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 4/14/2021 ROBERT DUFF
Sewer availability Cleared 4/14/2021 CECILIO NAVARRO
Low Impact Development Cleared 4/29/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/3/2021 CELINA MORENO
Trees in Parkway Cleared 5/20/2021 JOHN KIM

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/4/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 8/31/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Partial Approval JOAQUIN GREENOUGH
Insulation 9/1/2021 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Approved JOAQUIN GREENOUGH
HVAC-Rough 10/15/2021 Partial Inspection ANTHONY EGSON
PLUMBING-Rough 10/15/2021 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/18/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 10/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/19/2021 Conditional Approval ALEJANDRO DE ARTOLA
Green Building Rough 10/19/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 10/19/2021 Approved ALEJANDRO DE ARTOLA
Insulation 10/19/2021 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 10/19/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/28/2021 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 10/28/2021 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 12/14/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 12/15/2021 Approved JOAQUIN GREENOUGH
Final 12/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 12/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 12/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 12/15/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/12/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 1/12/2022 Approved JOAQUIN GREENOUGH
Final 1/12/2022 Partial Inspection JOAQUIN GREENOUGH
Green Building Final 1/12/2022 Approved JOAQUIN GREENOUGH
HVAC-Final 1/12/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Final 1/12/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 1/12/2022 Partial Inspection JOAQUIN GREENOUGH
Smoke Detectors 1/12/2022 Approved JOAQUIN GREENOUGH
Final 1/19/2022 Partial Inspection JOAQUIN GREENOUGH
Service/Power Release 1/19/2022 Approved JOAQUIN GREENOUGH
Final 1/20/2022 OK to Issue CofO JOAQUIN GREENOUGH
Service/Power Release 1/20/2022 Approved JOAQUIN GREENOUGH