230-230 1/2 E 101ST ST 90003
Certificate Information: 230-230 1/2 E 101ST ST 90003
- Application / Permit
- 21010-10000-01197
- Plan Check / Job No.
- B21LA04559
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 11/19/2021
- Issuing Office
- Current Status
- CofO Issued on 6/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | STARR CHEN |
| Corrections Issued | 3/24/2021 | STARR CHEN |
| Quality Review Completed | 3/28/2021 | HERNAN ARREOLA |
| Plan Check Approved | 7/30/2021 | STARR CHEN |
| Issued | 11/19/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| CofO in Progress | 6/15/2022 | JOHN KLARIN |
| CofO Issued | 6/17/2022 | DEROLD HAUFF |
| Permit Finaled | 6/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2021 | WALLIE JONG |
| Permit | Cleared | 4/19/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | WALLIE JONG |
| Sewer availability | Cleared | 5/3/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 5/10/2021 | ROBERT DUFF |
| Trees in Parkway | Cleared | 5/13/2021 | JOHN KIM |
| Low Impact Development | Cleared | 5/24/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/2/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/22/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 1/12/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | EUGENE CASSIDY |
| Insulation | 1/13/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 3/9/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 3/9/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 3/9/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/9/2022 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 3/9/2022 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 3/9/2022 | Approved | JOHN KLARIN |
| Insulation | 3/11/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 3/25/2022 | Not Ready for Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 3/25/2022 | Not Ready for Inspection | JOHN KLARIN |
| Drywall Nailing | 4/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/4/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 5/26/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/7/2022 | Approved | JOHN KLARIN |
| Final | 6/7/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 6/7/2022 | Approved | JOHN KLARIN |
| HVAC-Final | 6/7/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 6/7/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 6/7/2022 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 6/7/2022 | Approved | JOHN KLARIN |
| Final | 6/14/2022 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 6/14/2022 | Approved | JOHN KLARIN |
| Service/Power Release | 6/15/2022 | Approved | JOHN KLARIN |