7922 N FAIR AVE 91352

Certificate Information: 7922 N FAIR AVE 91352

Application / Permit
21010-10000-01191
Plan Check / Job No.
B21LA04522
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached ADU in Rear.
Permit Issued
Issued on 7/9/2021
Issuing Office
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 JOE VO
Corrections Issued 3/20/2021 JOE VO
Quality Review Completed 3/25/2021 MICHAEL PEREZ
Plan Check Approved 7/5/2021 JOE VO
Issued 7/9/2021 APPLICANT
CofO in Progress 2/10/2022 CHRISTOPHER DELLEFIELD
No Progress 3/2/2022 CHRISTOPHER DELLEFIELD
CofO in Progress 3/23/2022 DAVID MATSON
CofO Issued 6/30/2022 MICHAEL SMITH
Permit Finaled 6/30/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/25/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/26/2021 LEE GUILBEAUX
Sewer availability Cleared 3/26/2021 LEE GUILBEAUX
Clean Up Green Up Cleared 3/31/2021 LAUREN PADICK
Hydrant and Access approval Cleared 5/7/2021 JOHN CONNEALLY
Low Impact Development Cleared 6/11/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/15/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/8/2021 Corrections Issued JOHN HAYES
Underground Mechanical 9/10/2021 Approved JOHN HAYES
Footing/Foundation/Slab 9/28/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 11/5/2021 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 11/5/2021 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/16/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 11/16/2021 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 11/16/2021 Approved CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 11/16/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/19/2021 Approved CHRISTOPHER DELLEFIELD
Insulation 11/19/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 11/19/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 11/19/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 11/30/2021 Approved WILLIAM WREN
ELECTRICAL-Final 1/31/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 1/31/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 1/31/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 1/31/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 1/31/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 1/31/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 1/31/2022 Approved CHRISTOPHER DELLEFIELD
Final 2/8/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/8/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 2/8/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/10/2022 Approved CHRISTOPHER DELLEFIELD
Final 2/10/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 2/10/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/10/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 2/10/2022 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 3/2/2022 Corrections Issued CHRISTOPHER DELLEFIELD