226-228 E 101ST ST 90003

Certificate Information: 226-228 E 101ST ST 90003

Application / Permit
21010-10000-01188
Plan Check / Job No.
B21LA04474
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR
Permit Issued
Issued on 11/23/2021
Issuing Office
Current Status
CofO Issued on 9/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 SERGIO GUTIERREZ
Corrections Issued 3/22/2021 SERGIO GUTIERREZ
Quality Review Completed 3/25/2021 FARUK SEZER
Building Plans Picked Up 3/30/2021 APPLICANT
Applicant returned to address corrections 6/17/2021 SERGIO GUTIERREZ
Plan Check Approved 7/16/2021 SERGIO GUTIERREZ
Issued 11/23/2021 APPLICANT
CofO in Progress 7/6/2022 JOHN KLARIN
Permit Finaled 9/11/2022 DEROLD HAUFF
CofO Issued 9/11/2022 DEROLD HAUFF
Permit Finaled 9/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/13/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/13/2021 JEANIE LAM
Highway dedication Cleared 4/13/2021 JEANIE LAM
Sewer availability Cleared 4/13/2021 JEANIE LAM
Hydrant and Access approval Cleared 5/20/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/4/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/7/2021 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 6/8/2021 DENZEL HENDERSON

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval EUGENE CASSIDY
Underground Mechanical 1/13/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Partial Approval EUGENE CASSIDY
Insulation 1/14/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 3/9/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 3/9/2022 Approved JOHN KLARIN
Green Building Rough 3/9/2022 Approved JOHN KLARIN
HVAC-Rough 3/9/2022 Approved JOHN KLARIN
PLUMBING-Rough 3/9/2022 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 3/9/2022 Approved JOHN KLARIN
Verify Sprinkler Sign Off 3/9/2022 Approved JOHN KLARIN
Insulation 3/10/2022 Approved JOHN KLARIN
Drywall Nailing 3/25/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 3/25/2022 Approved JOHN KLARIN
ELECTRICAL-Final 5/26/2022 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Final 6/7/2022 Approved JOHN KLARIN
Final 6/7/2022 Corrections Issued JOHN KLARIN
Green Building Final 6/7/2022 Approved JOHN KLARIN
HVAC-Final 6/7/2022 Approved JOHN KLARIN
PLUMBING-Final 6/7/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 6/7/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 6/7/2022 Approved JOHN KLARIN
Final 6/14/2022 No Access for Inspection SHAVONNE ESPINOZA
Service/Power Release 6/14/2022 No Access for Inspection SHAVONNE ESPINOZA
Final 6/27/2022 Not Ready for Inspection JOHN KLARIN
Service/Power Release 6/27/2022 Approved JOHN KLARIN
Final 7/5/2022 OK to Issue CofO JOHN KLARIN
Service/Power Release 7/5/2022 Approved JOHN KLARIN