NEW (19' X 29') 513 SF 3-CAR GARAGE. “Contractor will perform both demo, Per#21019-10000-02444 and new construction onsite, Per#21010-10000-01170 & 21010-1000-01171”
Permit Issued
Issued on 2/4/2022
Issuing Office
Current Status
CofO Issued on 2/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 VIVIAN LAO
Corrections Issued 3/24/2021 VIVIAN LAO
Quality Review Completed 3/24/2021 MICHAEL PEREZ
Applicant returned to address corrections 12/3/2021 VIVIAN LAO
Applicant returned to address corrections 12/14/2021 VIVIAN LAO
Applicant returned to address corrections 2/1/2022 VIVIAN LAO
Plan Check Approved 2/4/2022 VIVIAN LAO
Issued 2/4/2022 APPLICANT
CofO in Progress 2/7/2023 EUGENE CASSIDY
CofO Issued 2/8/2023 ANSON MAGLASANG
Permit Finaled 2/8/2023 ANSON MAGLASANG

Permit Application Clearance Information

"Q" conditions Cleared 4/27/2021 MAXFIELD VERMY
Hydrant and Access approval Cleared 6/2/2021 GILBERT URREA
Permit Cleared 6/3/2021 STEVE MELGAR
Sewer availability Cleared 6/3/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/24/2021 STEVE MELGAR
Low Impact Development Cleared 12/2/2021 TA ANH
Roof/Waste drainage to street Cleared 2/3/2022 STEVE MELGAR

Contact Information

Contractor Jasper Construction; Lic. No.: 760385-B 2017 LOMITA BLVD #2093      LOMITA, CA 90717
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/22/2022 Approved EUGENE CASSIDY
ELECTRICAL-Rough 6/22/2022 Approved EUGENE CASSIDY
Green Building Rough 6/22/2022 Approved EUGENE CASSIDY
METHANE-Rough 6/22/2022 Approved EUGENE CASSIDY
Drywall Nailing 6/30/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/26/2022 Approved EUGENE CASSIDY
Final 10/26/2022 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 10/26/2022 Approved EUGENE CASSIDY
Green Building Final 10/26/2022 Approved EUGENE CASSIDY
METHANE-Barrier 10/26/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 10/26/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/26/2022 Not Required EUGENE CASSIDY
Smoke Detectors 10/26/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 1/24/2023 Approved EUGENE CASSIDY
Final 1/24/2023 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 1/24/2023 Approved EUGENE CASSIDY
PLUMBING-Final 1/24/2023 Approved EUGENE CASSIDY
Final 2/6/2023 OK to Issue CofO EUGENE CASSIDY