205-207 W G ST 90744
Certificate Information: 205-207 W G ST 90744
- Application / Permit
- 21010-10000-01170
- Plan Check / Job No.
- B21LA04431
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW (68' X 26') 3491 SF 2-STORY DUPLEX.(1 OF 2).
- Permit Issued
- Issued on 2/4/2022
- Issuing Office
- Current Status
- CofO Issued on 2/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | VIVIAN LAO |
| Corrections Issued | 3/24/2021 | VIVIAN LAO |
| Quality Review Completed | 3/24/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 12/3/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 12/14/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 2/1/2022 | VIVIAN LAO |
| Plan Check Approved | 2/4/2022 | VIVIAN LAO |
| Issued | 2/4/2022 | APPLICANT |
| CofO in Progress | 2/7/2023 | EUGENE CASSIDY |
| Permit Finaled | 2/8/2023 | ANSON MAGLASANG |
| CofO Issued | 2/8/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/8/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/27/2021 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 6/2/2021 | GILBERT URREA |
| Address approval | Cleared | 6/3/2021 | STEVE MELGAR |
| Permit | Cleared | 6/3/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 6/24/2021 | STEVE MELGAR |
| Low Impact Development | Cleared | 12/2/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/3/2022 | STEVE MELGAR |
Contact Information
| Contractor | Jasper Construction; Lic. No.: 760385-B | 2017 LOMITA BLVD #2093 LOMITA, CA 90717 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/14/2022 | Approved | JOHN KLARIN |
| METHANE-Barrier | 3/14/2022 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 3/14/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 5/16/2022 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 5/18/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/22/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/22/2022 | Conditional Approval | EUGENE CASSIDY |
| Green Building Rough | 6/22/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 6/22/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 6/22/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/22/2022 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/22/2022 | Approved | EUGENE CASSIDY |
| Insulation | 6/27/2022 | Conditional Approval | EUGENE CASSIDY |
| Drywall Nailing | 6/30/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/14/2022 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/26/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/26/2022 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 10/26/2022 | Approved | EUGENE CASSIDY |
| HVAC-Final | 10/26/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/26/2022 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 1/23/2023 | No Access for Inspection | EUGENE CASSIDY |
| Service/Power Release | 1/23/2023 | No Access for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/24/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 1/24/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 1/24/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/6/2023 | Approved | EUGENE CASSIDY |
| Final | 2/6/2023 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 2/6/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 2/6/2023 | Approved | EUGENE CASSIDY |