7742 S ISIS AVE 90045

Certificate Information: 7742 S ISIS AVE 90045

Application / Permit
21010-10000-01161
Plan Check / Job No.
B21LA04412
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SINGLE FAMILY DWELLING RESIDENCE WITH ATTACHED GARAGE
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 3/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 SERGIO GUTIERREZ
Corrections Issued 3/16/2021 SERGIO GUTIERREZ
Quality Review Completed 3/25/2021 FARUK SEZER
Plan Check Approved 7/15/2021 SERGIO GUTIERREZ
Issued 9/28/2021 APPLICANT
Building Plans Picked Up 10/6/2021 APPLICANT
CofO in Progress 3/3/2023 HERBERT GIRON
Permit Finaled 3/9/2023 DANIEL ORRANTE
CofO Issued 3/9/2023 DANIEL ORRANTE
Permit Finaled 3/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 4/8/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/9/2021 DINAH GARIN
Sewer availability Cleared 4/9/2021 DINAH GARIN
Specific Plan Cleared 5/18/2021 VALERIA CEJA
Hydrant and Access approval Cleared 5/20/2021 JOHN CONNEALLY
Driveway location Cleared 6/21/2021 VALERIA CEJA
Low Impact Development Cleared 6/23/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/25/2021 DINAH GARIN
GPI Written Notices Cleared 7/15/2021 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 7/15/2021 SERGIO GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Behshid,, Farshid; Lic. No.: S4585 4647 ENCINAS DR      LA CANADA, CA 91011

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/28/2021 Partial Approval BOBBY KEY
Pre-Inspection 10/28/2021 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 11/3/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 11/3/2021 Not Ready for Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 11/8/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 2/2/2022 Approved BOBBY KEY
PLUMBING-Rough 2/2/2022 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 2/24/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 2/24/2022 Approved BOBBY KEY
Green Building Rough 2/24/2022 Corrections Issued BOBBY KEY
HVAC-Rough 2/24/2022 Approved BOBBY KEY
PLUMBING-Rough 2/24/2022 Approved BOBBY KEY
Sewer 2/24/2022 Approved BOBBY KEY
Verify Sprinkler Sign Off 2/24/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 3/25/2022 Approved BOBBY KEY
Green Building Rough 3/25/2022 Approved BOBBY KEY
Verify Sprinkler Sign Off 3/25/2022 Approved BOBBY KEY
Insulation 4/7/2022 Approved BOBBY KEY
Drywall Nailing 4/26/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/26/2022 Partial Approval RYAN SALAZAR
Shower Pan 5/10/2022 Approved BOBBY KEY
Interior/Exterior Lathing 5/26/2022 Approved BOBBY KEY
ELECTRICAL-Final 9/1/2022 Partial Approval BOBBY KEY
Final 9/1/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Final 9/13/2022 Approved BOBBY KEY
Final 9/13/2022 Corrections Issued BOBBY KEY
Green Building Final 9/13/2022 Approved BOBBY KEY
HVAC-Final 9/13/2022 Approved BOBBY KEY
PLUMBING-Final 9/13/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Not Ready BOBBY KEY
Service/Power Release 9/13/2022 Approved BOBBY KEY
Smoke Detectors 9/13/2022 Approved BOBBY KEY
ELECTRICAL-Final 3/2/2023 Approved HERBERT GIRON
Final 3/2/2023 OK to Issue CofO HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Approved HERBERT GIRON