3218 E 3RD ST 90063
Certificate Information: 3218 E 3RD ST 90063
- Application / Permit
- 21010-10000-01153
- Plan Check / Job No.
- B21LA04396
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED GARAGE CONVERSION TO ADU PER STATE LAW
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 10/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2021 | CARLOS MONTES |
| Corrections Issued | 3/10/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 4/21/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 4/26/2021 | CARLOS MONTES |
| Plan Check Approved | 4/28/2021 | CARLOS MONTES |
| Issued | 5/20/2021 | APPLICANT |
| CofO in Progress | 6/28/2023 | FREDDIE RIVERA |
| No Progress | 9/26/2023 | FREDDIE RIVERA |
| CofO in Progress | 10/10/2023 | SCOTT FINNILA |
| CofO in Progress | 10/11/2023 | FREDDIE RIVERA |
| Permit Finaled | 10/11/2023 | DEROLD HAUFF |
| CofO Issued | 10/11/2023 | DEROLD HAUFF |
| Permit Finaled | 10/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/12/2021 | JEANIE LAM |
| Clean Up Green Up | Cleared | 3/15/2021 | RUBEN VASQUEZ |
| Grading Pre-Inspection | Cleared | 4/5/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Kafe Design & Construction; Lic. No.: 977712-B | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/18/2021 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 8/18/2021 | Not Ready for Inspection | COREY HUPP |
| METHANE-Rough | 8/18/2021 | Corrections Issued | COREY HUPP |
| PLUMBING-Rough | 8/18/2021 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 8/20/2021 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 9/1/2021 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/8/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Partial Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 9/23/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 9/27/2021 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 10/13/2021 | Partial Approval | ROBERT VORHIS |
| Deputy Drilled-In Anchors | 10/29/2021 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 10/29/2021 | Partial Approval | ROBERT VORHIS |
| Rough-Elec/Plmb/HVAC | 11/8/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/12/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/12/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 11/12/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 11/12/2021 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 11/12/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/7/2021 | Partial Inspection | AMY COLIN |
| Insulation | 12/7/2021 | Corrections Issued | AMY COLIN |
| Insulation | 12/9/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 1/26/2022 | No Access for Inspection | ADAM ESCOTO |
| Insulation | 2/10/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 3/25/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 4/20/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Green Building Rough | 4/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 4/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 5/13/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 5/13/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 5/13/2022 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 5/13/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/6/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 6/6/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/6/2022 | Partial Inspection | FREDDIE RIVERA |
| Drywall Nailing | 6/13/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 6/27/2022 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 8/4/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/27/2022 | Partial Approval | FREDDIE RIVERA |
| Final | 10/27/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/27/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 10/27/2022 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Final | 10/27/2022 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 10/27/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/21/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 11/21/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 11/21/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 11/21/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 11/21/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 12/19/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 12/19/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 3/17/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 3/17/2023 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 3/17/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 3/22/2023 | Corrections Issued | FREDDIE RIVERA |
| Final | 3/22/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 3/22/2023 | Approved | FREDDIE RIVERA |
| HVAC-Final | 3/22/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 3/22/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/4/2023 | Partial Approval | FREDDIE RIVERA |
| Final | 4/4/2023 | Partial Approval | FREDDIE RIVERA |
| HVAC-Final | 4/4/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 4/4/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/10/2023 | Approved | FREDDIE RIVERA |
| HVAC-Final | 4/10/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 4/10/2023 | Corrections Issued | FREDDIE RIVERA |
| Final | 6/27/2023 | OK to Issue CofO | FREDDIE RIVERA |
| PLUMBING-Final | 6/27/2023 | Approved | FREDDIE RIVERA |