808 1/2 W 56TH ST 90037

Certificate Information: 808 1/2 W 56TH ST 90037

Application / Permit
21010-10000-01141
Plan Check / Job No.
B21LA04355
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** new adu
Permit Issued
Issued on 7/21/2022
Issuing Office
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 ARSALAN SHABESTARI
Corrections Issued 3/28/2021 ARSALAN SHABESTARI
Quality Review Completed 4/1/2021 MICHAEL PEREZ
Applicant returned to address corrections 5/2/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 6/21/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 10/27/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 6/21/2022 ARSALAN SHABESTARI
Plan Check Approved 7/12/2022 ARSALAN SHABESTARI
Issued 7/21/2022 APPLICANT
CofO in Progress 9/27/2024 CRAIG DAVIS
Permit Finaled 11/1/2024 DEROLD HAUFF
CofO Issued 11/1/2024 DEROLD HAUFF
Permit Finaled 11/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/13/2021 THOMAS LANG
Sewer availability Cleared 4/13/2021 THOMAS LANG
CPC Cleared 8/4/2021 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 8/10/2021 THOMAS LANG
Hydrant and Access approval Cleared 9/12/2021 RUEL COLE
Low Impact Development Cleared 4/25/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 4/28/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2022 Corrections Issued RYAN SALAZAR
Underground Mechanical 8/18/2022 Partial Inspection RYAN SALAZAR
Footing/Foundation/Slab 10/4/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 11/1/2022 No Access for Inspection SABAS ALONSO
Footing/Foundation/Slab 11/3/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 12/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 12/7/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 12/7/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 4/14/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 4/14/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 4/25/2023 Approved SABAS ALONSO
PLUMBING-Rough 4/25/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved SABAS ALONSO
Green Building Rough 7/6/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 7/6/2023 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 7/6/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 7/25/2023 Approved CHARLES BOGHOSKHAN
Green Building Rough 7/25/2023 Approved CHARLES BOGHOSKHAN
Insulation 8/17/2023 Corrections Issued DONALD CRICHLOW
Interior/Exterior Lathing 8/17/2023 Approved DONALD CRICHLOW
Insulation 9/14/2023 Approved SABAS ALONSO
Drywall Nailing 9/29/2023 Approved RONNIE MINDANAO
Final 1/9/2024 Not Ready for Inspection SABAS ALONSO
Green Building Final 1/9/2024 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 1/9/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 1/9/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 2/29/2024 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Final 2/29/2024 Not Ready for Inspection RONNIE MINDANAO
Pre-Inspection 2/29/2024 Not Ready for Inspection RONNIE MINDANAO
Underground Mechanical 3/4/2024 Corrections Issued RONNIE MINDANAO
Underground Mechanical 3/14/2024 Corrections Issued CRAIG DAVIS
Underground Mechanical 3/28/2024 Partial Approval CRAIG DAVIS
Underground Mechanical 4/23/2024 Approved CRAIG DAVIS
Final 6/11/2024 Corrections Issued CRAIG DAVIS
Green Building Final 6/11/2024 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Not Ready CRAIG DAVIS
Service/Power Release 6/11/2024 Partial Inspection CRAIG DAVIS
Smoke Detectors 6/11/2024 Approved CRAIG DAVIS
Final 9/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 9/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/26/2024 Approved CRAIG DAVIS
Final 9/26/2024 OK to Issue CofO CRAIG DAVIS
HVAC-Final 9/26/2024 Approved CRAIG DAVIS
PLUMBING-Final 9/26/2024 Approved CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Approved CRAIG DAVIS
Service/Power Release 9/26/2024 Approved CRAIG DAVIS