8943-8945 N SWINTON AVE 91343
Certificate Information: 8943-8945 N SWINTON AVE 91343
- Application / Permit
- 21010-10000-01112
- Plan Check / Job No.
- B21LA04223
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- -CONVERTING EXT'G 2 CAR GARAGE TO ADU WITH LIVING AREA, KITCHEN AND A BATHROOM (363 SQ. FT.)
- Permit Issued
- Issued on 6/28/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2021 | VU NGUYEN |
| Corrections Issued | 3/14/2021 | VU NGUYEN |
| Applicant returned to address corrections | 4/12/2021 | VU NGUYEN |
| Applicant returned to address corrections | 5/4/2021 | VU NGUYEN |
| Plan Check Approved | 5/11/2021 | VU NGUYEN |
| Issued | 6/28/2021 | APPLICANT |
| CofO in Progress | 3/12/2022 | RAUL OLAGI |
| CofO Issued | 6/20/2022 | MICHAEL SMITH |
| Permit Finaled | 6/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/6/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2021 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/14/2021 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/14/2021 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 10/14/2021 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 10/14/2021 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 10/14/2021 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/21/2021 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 10/21/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 10/21/2021 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 10/21/2021 | Conditional Approval | RAUL OLAGI |
| PLUMBING-Rough | 10/21/2021 | Approved | RAUL OLAGI |
| Insulation | 10/28/2021 | Approved | ALAN MORELOS |
| Drywall Nailing | 11/17/2021 | Partial Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/23/2021 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 11/23/2021 | Approved | RAUL OLAGI |
| HVAC-Rough | 11/23/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/25/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 2/25/2022 | Corrections Issued | RAUL OLAGI |
| Final | 2/25/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/25/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 2/25/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 2/25/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 2/25/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 3/11/2022 | Approved | RAUL OLAGI |
| Final | 3/11/2022 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 3/11/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 3/11/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 3/11/2022 | Approved | RAUL OLAGI |