809 N STANLEY AVE 90046
Certificate Information: 809 N STANLEY AVE 90046
- Application / Permit
- 21010-10000-01111
- Plan Check / Job No.
- B21LA04220
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing two garage into an ADU.
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2021 | JOE VO |
| Corrections Issued | 3/10/2021 | JOE VO |
| Plan Check Approved | 4/21/2022 | JOE VO |
| Plan Check Approved | 5/6/2022 | JOE VO |
| Issued | 5/17/2022 | APPLICANT |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
| CofO Issued | 3/8/2024 | DEROLD HAUFF |
| Permit Finaled | 3/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/29/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 5/5/2022 | CELINA MORENO |
| Sewer availability | Cleared | 5/5/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/7/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/3/2022 | No Access for Inspection | MICHAEL LEWIS |
| Green Building Rough | 11/3/2022 | No Access for Inspection | MICHAEL LEWIS |
| METHANE-Rough | 11/3/2022 | No Access for Inspection | MICHAEL LEWIS |
| Wood Frame | 11/3/2022 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 11/4/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/4/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 11/4/2022 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 11/4/2022 | Approved | MICHAEL LEWIS |
| Wood Frame | 11/4/2022 | Approved | MICHAEL LEWIS |
| Insulation | 11/10/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 1/4/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/17/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | LILIANA PORTILLO |
| Final | 1/19/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 1/19/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 1/19/2024 | Approved | LILIANA PORTILLO |
| METHANE-Final | 1/19/2024 | Approved | LILIANA PORTILLO |
| METHANE-Rough | 1/19/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/19/2024 | SGSOV Not Required | LILIANA PORTILLO |
| Smoke Detectors | 1/19/2024 | Approved | LILIANA PORTILLO |
| Final | 2/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 2/20/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Special/Order Compliance | 2/20/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 2/29/2024 | Partial Approval | AMIR NAZARIAN |
| Green Building Final | 2/29/2024 | Approved | AMIR NAZARIAN |