809 N STANLEY AVE 90046

Certificate Information: 809 N STANLEY AVE 90046

Application / Permit
21010-10000-01111
Plan Check / Job No.
B21LA04220
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing two garage into an ADU.
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 3/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2021 APPLICANT
Assigned to Plan Check Engineer 3/9/2021 JOE VO
Corrections Issued 3/10/2021 JOE VO
Plan Check Approved 4/21/2022 JOE VO
Plan Check Approved 5/6/2022 JOE VO
Issued 5/17/2022 APPLICANT
Permit Finaled 3/8/2024 DEROLD HAUFF
CofO Issued 3/8/2024 DEROLD HAUFF
Permit Finaled 3/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 3/29/2021 WALTER RAMIREZ
Address approval Cleared 5/5/2022 CELINA MORENO
Sewer availability Cleared 5/5/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/6/2022 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/3/2022 No Access for Inspection MICHAEL LEWIS
Green Building Rough 11/3/2022 No Access for Inspection MICHAEL LEWIS
METHANE-Rough 11/3/2022 No Access for Inspection MICHAEL LEWIS
Wood Frame 11/3/2022 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 11/4/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Approved MICHAEL LEWIS
Footing/Foundation/Slab 11/4/2022 Approved MICHAEL LEWIS
HVAC-Rough 11/4/2022 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 11/4/2022 Approved MICHAEL LEWIS
Wood Frame 11/4/2022 Approved MICHAEL LEWIS
Insulation 11/10/2022 Approved MICHAEL LEWIS
Drywall Nailing 1/4/2023 Approved MICHAEL LEWIS
Shower Pan 1/17/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/19/2024 Approved LILIANA PORTILLO
Final 1/19/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 1/19/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 1/19/2024 Approved LILIANA PORTILLO
METHANE-Final 1/19/2024 Approved LILIANA PORTILLO
METHANE-Rough 1/19/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/19/2024 SGSOV Not Required LILIANA PORTILLO
Smoke Detectors 1/19/2024 Approved LILIANA PORTILLO
Final 2/20/2024 Corrections Issued AMIR NAZARIAN
Green Building Final 2/20/2024 Not Ready for Inspection AMIR NAZARIAN
Special/Order Compliance 2/20/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 2/29/2024 Partial Approval AMIR NAZARIAN
Green Building Final 2/29/2024 Approved AMIR NAZARIAN