718 N TERRACE 49 90042
Certificate Information: 718 N TERRACE 49 90042
- Application / Permit
- 21010-10000-01092
- Plan Check / Job No.
- B21LA04162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF ONE ACCESSORY DWELLING UNIT ABOVE DETACHED PARKING GARAGE PER DETACHED ADU ORDINANCE
- Permit Issued
- Issued on 9/23/2021
- Issuing Office
- Current Status
- CofO Issued on 9/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | CARLOS MONTES |
| Corrections Issued | 3/13/2021 | CARLOS MONTES |
| Quality Review Completed | 3/22/2021 | LARRY LEE |
| Applicant returned to address corrections | 5/3/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 8/24/2021 | CARLOS MONTES |
| Plan Check Approved | 9/17/2021 | CARLOS MONTES |
| Issued | 9/23/2021 | APPLICANT |
| CofO in Progress | 8/17/2022 | OSVALDO PARAMO |
| CofO in Progress | 8/17/2022 | OSVALDO PARAMO |
| Permit Finaled | 9/2/2022 | DEROLD HAUFF |
| CofO Issued | 9/2/2022 | DEROLD HAUFF |
| Permit Finaled | 9/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 4/8/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 4/8/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 4/8/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 4/8/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 4/8/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2021 | WALLIE JONG |
| Sewer availability | Cleared | 4/12/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 4/28/2021 | BRIAN MILLER |
| GPI Written Notices | Cleared | 5/4/2021 | CARLOS MONTES |
| Hydrant and Access approval | Cleared | 5/21/2021 | MATTHEW CRAIG |
| Specific Plan | Cleared | 6/3/2021 | DYLAN LAWRENCE |
| Miscellaneous | Cleared | 6/4/2021 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 8/26/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/27/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Shu; Lic. No.: C90391 | 136 LOST HILLS IRVINE, CA 92618 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/30/2021 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/5/2021 | Approved | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 10/8/2021 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/12/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/4/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/12/2021 | Corrections Issued | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 11/15/2021 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/19/2021 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2021 | Corrections Issued | OSVALDO PARAMO |
| Deputy Wood Construction | 12/16/2021 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2022 | Partial Inspection | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Special/Order Compliance | 2/2/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 2/9/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/1/2022 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 3/1/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/8/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 3/8/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/8/2022 | Approved | OSVALDO PARAMO |
| Deputy Wood Construction | 3/23/2022 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Approved | OSVALDO PARAMO |
| Wood Frame | 3/29/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/6/2022 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 4/6/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/8/2022 | Approved | AMY COLIN |
| Drywall Nailing | 4/19/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/4/2022 | Approved | OSVALDO PARAMO |
| Shower Pan | 5/4/2022 | Approved | OSVALDO PARAMO |
| Final | 6/6/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Gas Test | 6/6/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 6/6/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 6/9/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/13/2022 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 6/13/2022 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Approved | OSVALDO PARAMO |
| Final | 6/15/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 6/15/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Final | 6/16/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/17/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 6/22/2022 | Partial Inspection | OSVALDO PARAMO |
| Final | 7/25/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 7/25/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/25/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 8/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 8/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Sewer | 8/1/2022 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 8/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 8/5/2022 | Approved | OSVALDO PARAMO |
| Service/Power Release | 8/5/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Sewer | 8/5/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 8/9/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 8/9/2022 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/9/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 8/10/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Service/Power Release | 8/10/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 8/10/2022 | Corrections Issued | OSVALDO PARAMO |
| Final | 8/15/2022 | OK to Issue CofO | OSVALDO PARAMO |
| Service/Power Release | 8/15/2022 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 8/15/2022 | Approved | OSVALDO PARAMO |