4846-4846 1/2 W 17TH ST 90019
Certificate Information: 4846-4846 1/2 W 17TH ST 90019
- Application / Permit
- 21010-10000-01079
- Plan Check / Job No.
- B21LA04088
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 36'X33'-4" 3-STORY DUPLEX 3,364 SF WITH 2-CAR GARAGE 330 SF IN THE REAR OF LOT. 2 OF 2
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 2/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 3/24/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 4/4/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/3/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 1/14/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 1/20/2022 | CHUNG-WEN CHUANG |
| Plan Check Approved | 1/26/2022 | CHUNG-WEN CHUANG |
| Issued | 2/10/2022 | APPLICANT |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| CofO in Progress | 2/22/2023 | CALEB MEISTER |
| Permit Finaled | 2/26/2023 | DEROLD HAUFF |
| CofO Issued | 2/26/2023 | DEROLD HAUFF |
| Permit Finaled | 2/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 10/26/2021 | KHAING AYE |
| Hydrant and Access approval | Cleared | 11/2/2021 | JOHN CONNEALLY |
| Address approval | Cleared | 12/9/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 12/9/2021 | STEVE MELGAR |
| Flood clearance | Cleared | 12/13/2021 | TIFFANY WONG |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3627 E FIRST STREET LOS ANGELES, CA 90063 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 2/23/2022 | Approved | STUART CHAPMAN |
| Deputy Methane Barrier | 2/28/2022 | Approved | STUART CHAPMAN |
| FLOOD-Elevation Certificate | 3/1/2022 | Approved | STUART CHAPMAN |
| Final | 3/1/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/1/2022 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 3/1/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 3/1/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 3/17/2022 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 3/17/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/20/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/20/2022 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 6/20/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 6/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 6/20/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Rough | 6/20/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 6/20/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/20/2022 | Approved | STUART CHAPMAN |
| Insulation | 6/27/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 7/6/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 7/6/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/6/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/2/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 2/2/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 2/2/2023 | Approved | CALEB MEISTER |
| Final | 2/2/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 2/2/2023 | Approved | CALEB MEISTER |
| HVAC-Final | 2/2/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 2/2/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 2/2/2023 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 2/2/2023 | Approved | CALEB MEISTER |
| Final | 2/17/2023 | OK to Issue CofO | CALEB MEISTER |
| Service/Power Release | 2/17/2023 | Approved | CALEB MEISTER |