9017 S HOOVER ST 90044

Certificate Information: 9017 S HOOVER ST 90044

Application / Permit
21010-10000-01075
Plan Check / Job No.
B21LA04078
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE STORY ACCESSORY DWELLING UNIT (ADU) PER LAMC 12.22 A.33 (c)-(d) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 5/5/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 SERGIO GUTIERREZ
Corrections Issued 3/14/2021 SERGIO GUTIERREZ
Applicant returned to address corrections 8/25/2021 SERGIO GUTIERREZ
Building Plans Picked Up 8/30/2021 APPLICANT
Applicant returned to address corrections 9/21/2022 JOSEPH RAFOLS
Applicant returned to address corrections 2/22/2023 CRISTINA SALAZAR
Plan Check Approved 5/1/2023 RICARDO RAMIREZ
Issued 5/5/2023 APPLICANT
CofO in Progress 7/11/2024 MICHAEL LEWIS
CofO Issued 7/22/2024 DEROLD HAUFF
Permit Finaled 7/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/22/2021 MATTHEW CRAIG
Address approval Cleared 8/10/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/12/2022 JEANETTE VONG
Sewer availability Cleared 8/12/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/11/2023 TREVOR QUAN
Construction near power lines Cleared 4/14/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/8/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 8/3/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/3/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 10/5/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 10/5/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/24/2023 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved MICHAEL LEWIS
HVAC-Rough 10/24/2023 Approved MICHAEL LEWIS
Sewer 10/24/2023 Approved MICHAEL LEWIS
Underground Mechanical 10/24/2023 Approved MICHAEL LEWIS
Green Building Rough 11/20/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/20/2023 Approved MICHAEL LEWIS
Insulation 11/27/2023 Approved RONNIE MINDANAO
Drywall Nailing 1/8/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/8/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/28/2024 Conditional Approval MICHAEL LEWIS
Final 3/28/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 3/28/2024 Approved MICHAEL LEWIS
Green Building Final 3/28/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 3/28/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 3/28/2024 Corrections Issued MICHAEL LEWIS
Verify Sprinkler Sign Off 3/28/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/22/2024 Partial Inspection MICHAEL LEWIS
Final 5/22/2024 Partial Inspection MICHAEL LEWIS
Service/Power Release 5/22/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 5/22/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/10/2024 Approved MICHAEL LEWIS
Final 7/10/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 7/10/2024 Approved MICHAEL LEWIS