1015-1017 E VICTORIA AVE 90291

Certificate Information: 1015-1017 E VICTORIA AVE 90291

Application / Permit
21010-10000-01073
Plan Check / Job No.
B21LA04067
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADDITION TO (E) SFD FOR NEW ADU AND ATTACHED PATIO COVER PER LAMC 12.22 A.33(c)-(d), and (g)
Permit Issued
Issued on 5/11/2023
Issuing Office
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/10/2021 JOSEPH RAFOLS
Corrections Issued 3/17/2021 JOSEPH RAFOLS
Building Plans Picked Up 3/18/2021 APPLICANT
Applicant returned to address corrections 1/30/2023 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 3/1/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 5/11/2023 MAHNAZ NOURHASHEMI
Issued 5/11/2023 APPLICANT
CofO in Progress 1/12/2024 HERBERT GIRON
CofO in Progress 1/16/2024 HERBERT GIRON
CofO in Progress 2/1/2024 HERBERT GIRON
Permit Finaled 2/7/2024 DANIEL ORRANTE
CofO Issued 2/7/2024 DANIEL ORRANTE
Permit Finaled 2/7/2024 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 4/6/2021 MIGUEL GAMBOA
Address approval Cleared 4/13/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/23/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/23/2021 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 6/3/2021 KURT CORRAL
Specific Plan Cleared 6/3/2021 FREDDY GARCIA
Low Impact Development Cleared 12/22/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 12/23/2022 RAYMOND MUGAMBWA
Construction near power lines Cleared 5/2/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/16/2023 Partial Approval EVAN COOPER
Sewer 5/16/2023 Approved EVAN COOPER
Underground Mechanical 5/16/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/22/2023 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/25/2023 Approved EVAN COOPER
HVAC-Rough 7/25/2023 Corrections Issued EVAN COOPER
HVAC-Rough 7/27/2023 Approved EVAN COOPER
Interior/Exterior Lathing 7/27/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 7/31/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 8/2/2023 Corrections Issued HERBERT GIRON
Green Building Rough 8/2/2023 Approved HERBERT GIRON
PLUMBING-Rough 8/2/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/22/2023 Approved HERBERT GIRON
Verify Sprinkler Sign Off 8/22/2023 Approved HERBERT GIRON
Insulation 9/5/2023 Corrections Issued HERBERT GIRON
Insulation 9/6/2023 Not Ready for Inspection HERBERT GIRON
Drywall Nailing 9/8/2023 Approved HERBERT GIRON
Insulation 9/8/2023 Approved HERBERT GIRON
Drywall Nailing 9/11/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 9/18/2023 Approved HERBERT GIRON
ELECTRICAL-Final 1/3/2024 Corrections Issued HERBERT GIRON
HVAC-Final 1/3/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/3/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 1/11/2024 Corrections Issued HERBERT GIRON
Final 1/11/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 1/11/2024 Approved HERBERT GIRON
Green Building Final 1/11/2024 Approved HERBERT GIRON
HVAC-Final 1/11/2024 Approved HERBERT GIRON
PLUMBING-Final 1/11/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/11/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/11/2024 Approved HERBERT GIRON
ELECTRICAL-Final 1/12/2024 Approved HERBERT GIRON
Final 1/12/2024 Corrections Issued HERBERT GIRON
Final 1/16/2024 Corrections Issued HERBERT GIRON
Final 1/31/2024 OK to Issue CofO HERBERT GIRON