12917 W RUBENS AVE 90066

Certificate Information: 12917 W RUBENS AVE 90066

Application / Permit
21010-10000-01064
Plan Check / Job No.
B21LA04010
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SINGLE STORY ADDITION TO SFD AND RENOVATION OF EXISTING (492 FT) PER ENGINEER DESIGN
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
CofO Issued on 6/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/9/2021 RAHEL BEYENE
Corrections Issued 3/10/2021 RAHEL BEYENE
Applicant returned to address corrections 7/13/2021 RAHEL BEYENE
Plan Check Approved 7/15/2021 RAHEL BEYENE
Issued 7/26/2021 APPLICANT
Building Plans Picked Up 7/28/2021 APPLICANT
CofO in Progress 5/31/2022 STEPHANIE SWANSON
Permit Finaled 6/1/2022 DANIEL ORRANTE
CofO Issued 6/1/2022 DANIEL ORRANTE
Permit Finaled 6/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Food Service Establishment Cleared 3/10/2021 EMERLITA ALVAREZ
Eng Process Fee Ord 176,300 Cleared 3/24/2021 NIKTA MOUSAVI
Sewer availability Cleared 3/26/2021 NIKTA MOUSAVI
Low Impact Development Cleared 6/17/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 6/29/2021 NIKTA MOUSAVI

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/12/2021 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 8/17/2021 Approved BRENDAN LOONEY
METHANE-Barrier 8/17/2021 Approved BRENDAN LOONEY
METHANE-Subgrade 8/17/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval DEANDRE HOFFMAN
Deputy Wood Construction 10/26/2021 Approved JOHN KAYON
Gas Test 10/27/2021 Approved JOHN KAYON
HVAC-Rough 10/27/2021 Approved JOHN KAYON
PLUMBING-Rough 10/27/2021 Not Ready for Inspection JOHN KAYON
ELECTRICAL-Rough 11/1/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 11/1/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 11/3/2021 Corrections Issued JOHN KAYON
PLUMBING-Rough 11/3/2021 Approved JOHN KAYON
ELECTRICAL-Rough 11/30/2021 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Partial Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Approved DAVID FEILER
MERV13>=Rough 12/8/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 12/17/2021 Approved JOHN KAYON
Green Building Rough 12/17/2021 Approved JOHN KAYON
METHANE-Rough 12/17/2021 Approved JOHN KAYON
Insulation 1/7/2022 Approved JOHN KAYON
Drywall Nailing 1/20/2022 Approved JOHN KAYON
Interior/Exterior Lathing 1/20/2022 Approved JOHN KAYON
Shower Pan 1/26/2022 Approved KENNETH NAGLE
Interior/Exterior Lathing 2/8/2022 Approved CLAYTON GRAHAM
HVAC-Final 4/7/2022 Not Ready for Inspection DAVID FEILER
Service/Power Release 4/7/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 4/13/2022 Approved JESUS RODRIGUEZ
Service/Power Release 4/13/2022 Approved JESUS RODRIGUEZ
Smoke Detectors 4/13/2022 Approved JESUS RODRIGUEZ
HVAC-Final 5/12/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 5/12/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/12/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 5/12/2022 Approved JESUS RODRIGUEZ
Final 5/20/2022 Corrections Issued STEPHANIE SWANSON
Green Building Final 5/20/2022 Approved STEPHANIE SWANSON
HVAC-Final 5/20/2022 Approved STEPHANIE SWANSON
MERV13>=Final 5/20/2022 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 5/20/2022 SGSOV Approved STEPHANIE SWANSON
Final 5/31/2022 OK to Issue CofO STEPHANIE SWANSON