8508 S TRUXTON AVE 90045

Certificate Information: 8508 S TRUXTON AVE 90045

Application / Permit
21010-10000-01059
Plan Check / Job No.
B21LA03990
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Construct a new two story ADU unit at rear of propertyper Ordinance and LAMC 12.22 A.33(c)&(d). All work per Engineer Design.
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 4/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 ZAW HAN
Corrections Issued 3/18/2021 ZAW HAN
Quality Review Completed 3/24/2021 HERNAN ARREOLA
Plan Check Approved 6/14/2021 ZAW HAN
Issued 10/26/2021 APPLICANT
CofO in Progress 4/7/2022 BOBBY KEY
No Progress 4/15/2022 RICHARD STEINBACH
CofO in Progress 4/23/2022 RICHARD STEINBACH
Permit Finaled 4/26/2022 DANIEL ORRANTE
CofO Issued 4/26/2022 DANIEL ORRANTE
Permit Finaled 4/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/22/2021 DINAH GARIN
Specific Plan Cleared 3/23/2021 EDUARDO HERMOSO
CPC Cleared 3/31/2021 LOUIS ORTEGA
Sewer availability Cleared 3/31/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/7/2021 DINAH GARIN
Miscellaneous Cleared 4/7/2021 JENSON LEE
Construction near power lines Cleared 4/28/2021 RIDWAN HARDY
Construction within easement Cleared 4/28/2021 RIDWAN HARDY
Low Impact Development Cleared 5/12/2021 ANDRES COVARRUBIAS
Public Works-Highway Ded. Cleared 5/14/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 5/27/2021 DINAH GARIN

Contact Information

Contractor Greencast Construction Inc; Lic. No.: 1057881-B 6229 FALLBROOK AVENUE      WOODLAND HILLS, CA 91367
Engineer Durand,, Paul Henri; Lic. No.: NA4222       ,
Engineer Durand,, Paul Henri; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/29/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 10/29/2021 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 11/3/2021 Corrections Issued BOBBY KEY
PLUMBING-Rough 11/3/2021 Partial Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 11/9/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/22/2021 Partial Approval BOBBY KEY
PLUMBING-Rough 11/30/2021 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Partial Approval BOBBY KEY
Special/Order Compliance 12/17/2021 Corrections Issued BOBBY KEY
Special/Order Compliance 1/3/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 1/5/2022 Corrections Issued BOBBY KEY
HVAC-Rough 1/5/2022 Approved BOBBY KEY
PLUMBING-Rough 1/5/2022 Corrections Issued BOBBY KEY
Wood Frame 1/5/2022 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 1/10/2022 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 1/10/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 1/21/2022 Approved BOBBY KEY
ELECTRICAL-Rough 1/21/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Approved BOBBY KEY
Footing/Foundation/Slab 1/21/2022 Approved BOBBY KEY
Green Building Rough 1/21/2022 Approved BOBBY KEY
Insulation 1/21/2022 Approved BOBBY KEY
Interior/Exterior Lathing 1/21/2022 Partial Approval BOBBY KEY
Verify Sprinkler Sign Off 1/21/2022 Approved BOBBY KEY
Drywall Nailing 1/27/2022 Approved BOBBY KEY
Final 1/27/2022 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 2/10/2022 Partial Approval CLAYTON GRAHAM
Shower Pan 2/10/2022 Approved CLAYTON GRAHAM
ELECTRICAL-Final 3/17/2022 Corrections Issued BOBBY KEY
Final 3/17/2022 Corrections Issued BOBBY KEY
Green Building Final 3/17/2022 Approved BOBBY KEY
HVAC-Final 3/17/2022 Approved BOBBY KEY
PLUMBING-Final 3/17/2022 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 3/17/2022 Approved BOBBY KEY
ELECTRICAL-Final 3/22/2022 Approved BOBBY KEY
Final 3/22/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 3/22/2022 Approved BOBBY KEY
Final 4/7/2022 OK to Issue CofO BOBBY KEY
Special/Order Compliance 4/18/2022 Corrections Issued BOBBY KEY