8508 S TRUXTON AVE 90045
Certificate Information: 8508 S TRUXTON AVE 90045
- Application / Permit
- 21010-10000-01059
- Plan Check / Job No.
- B21LA03990
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Construct a new two story ADU unit at rear of propertyper Ordinance and LAMC 12.22 A.33(c)&(d). All work per Engineer Design.
- Permit Issued
- Issued on 10/26/2021
- Issuing Office
- Current Status
- CofO Issued on 4/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | ZAW HAN |
| Corrections Issued | 3/18/2021 | ZAW HAN |
| Quality Review Completed | 3/24/2021 | HERNAN ARREOLA |
| Plan Check Approved | 6/14/2021 | ZAW HAN |
| Issued | 10/26/2021 | APPLICANT |
| CofO in Progress | 4/7/2022 | BOBBY KEY |
| No Progress | 4/15/2022 | RICHARD STEINBACH |
| CofO in Progress | 4/23/2022 | RICHARD STEINBACH |
| Permit Finaled | 4/26/2022 | DANIEL ORRANTE |
| CofO Issued | 4/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2021 | DINAH GARIN |
| Specific Plan | Cleared | 3/23/2021 | EDUARDO HERMOSO |
| CPC | Cleared | 3/31/2021 | LOUIS ORTEGA |
| Sewer availability | Cleared | 3/31/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | DINAH GARIN |
| Miscellaneous | Cleared | 4/7/2021 | JENSON LEE |
| Construction near power lines | Cleared | 4/28/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/28/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/12/2021 | ANDRES COVARRUBIAS |
| Public Works-Highway Ded. | Cleared | 5/14/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/27/2021 | DINAH GARIN |
Contact Information
| Contractor | Greencast Construction Inc; Lic. No.: 1057881-B | 6229 FALLBROOK AVENUE WOODLAND HILLS, CA 91367 |
| Engineer | Durand,, Paul Henri; Lic. No.: NA4222 | , |
| Engineer | Durand,, Paul Henri; Lic. No.: S4222 | 611 N G ST OXNARD, CA 93030 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/29/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 10/29/2021 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 11/3/2021 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 11/3/2021 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 11/9/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/22/2021 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 11/30/2021 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 12/17/2021 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 1/3/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 1/5/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 1/5/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/5/2022 | Corrections Issued | BOBBY KEY |
| Wood Frame | 1/5/2022 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 1/10/2022 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/10/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/21/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 1/21/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 1/21/2022 | Approved | BOBBY KEY |
| Green Building Rough | 1/21/2022 | Approved | BOBBY KEY |
| Insulation | 1/21/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/21/2022 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 1/21/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 1/27/2022 | Approved | BOBBY KEY |
| Final | 1/27/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 2/10/2022 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 2/10/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 3/17/2022 | Corrections Issued | BOBBY KEY |
| Final | 3/17/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 3/17/2022 | Approved | BOBBY KEY |
| HVAC-Final | 3/17/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/17/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 3/17/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/22/2022 | Approved | BOBBY KEY |
| Final | 3/22/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 3/22/2022 | Approved | BOBBY KEY |
| Final | 4/7/2022 | OK to Issue CofO | BOBBY KEY |
| Special/Order Compliance | 4/18/2022 | Corrections Issued | BOBBY KEY |