1595-1597 W 35TH PL 90018

Certificate Information: 1595-1597 W 35TH PL 90018

Application / Permit
21010-10000-01058
Plan Check / Job No.
B21LA03985
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY DUPLEX WITH ATTACHED GARAGE.
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Issued on 5/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 JOHNNY WU
Corrections Issued 4/28/2021 JOHNNY WU
Quality Review Completed 4/30/2021 FARUK SEZER
Building Plans Picked Up 5/4/2021 APPLICANT
Applicant returned to address corrections 9/17/2021 JOHNNY WU
Applicant returned to address corrections 9/21/2021 JOHNNY WU
Plan Check Approved 9/22/2021 JOHNNY WU
Issued 9/27/2021 APPLICANT
CofO in Progress 4/2/2024 SABAS ALONSO
Permit Finaled 5/7/2024 DEROLD HAUFF
CofO Issued 5/7/2024 DEROLD HAUFF
Permit Finaled 5/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/21/2021 WALLIE JONG
Address approval Cleared 5/21/2021 WALLIE JONG
Permit Cleared 5/21/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/25/2021 WALLIE JONG
Sewer availability Cleared 5/25/2021 WALLIE JONG
Trees in Parkway Cleared 7/15/2021 JOHN KIM
Hydrant and Access approval Cleared 8/27/2021 MATTHEW CRAIG
Low Impact Development Cleared 9/8/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/9/2021 WALLIE JONG
Green Code Cleared 9/21/2021 JOHNNY WU

Contact Information

Contractor Limestone General Contractor; Lic. No.: 1023749-B 8905 VALLEY BLVD      ROSEMEAD, CA 91770
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Geologist Feucht,, Alex Thomas; Lic. No.: GEO4433 2443 EAGLE HARBOR DRIVE      HENDERSON, NV 890527136

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/9/2021 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 12/1/2021 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 12/1/2021 Corrections Issued SABAS ALONSO
METHANE-Barrier 12/1/2021 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 12/1/2021 Not Ready for Inspection SABAS ALONSO
Sewer 12/1/2021 Not Ready for Inspection SABAS ALONSO
Pre-Inspection 12/8/2021 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 1/13/2022 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/25/2022 Approved SABAS ALONSO
METHANE-Barrier 1/25/2022 Approved SABAS ALONSO
METHANE-Subgrade 1/25/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 4/21/2022 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval SABAS ALONSO
Pre-Inspection 5/12/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval HORACE FULTZ
ELECTRICAL-Final 6/27/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 6/27/2022 Approved SABAS ALONSO
PLUMBING-Rough 6/27/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 7/5/2022 Partial Approval SABAS ALONSO
HVAC-Rough 8/11/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/26/2022 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 8/26/2022 Approved JOAQUIN GREENOUGH
METHANE-Rough 8/26/2022 Partial Approval JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 8/26/2022 Approved JOAQUIN GREENOUGH
Insulation 9/8/2022 Partial Approval SABAS ALONSO
Insulation 9/30/2022 Approved SABAS ALONSO
Drywall Nailing 10/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 10/20/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 11/21/2022 Approved SABAS ALONSO
Sewer 12/28/2022 Approved SABAS ALONSO
ELECTRICAL-Final 5/5/2023 Approved SABAS ALONSO
PLUMBING-Final 5/5/2023 Approved SABAS ALONSO
HVAC-Final 5/23/2023 No Access for Inspection SABAS ALONSO
HVAC-Final 6/1/2023 Corrections Issued STUART CHAPMAN
HVAC-Final 7/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/24/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/31/2023 Approved ENRIQUE MIRELES
Final 7/31/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 7/31/2023 Approved ENRIQUE MIRELES
METHANE-Final 7/31/2023 Approved ENRIQUE MIRELES
METHANE-Rough 7/31/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 7/31/2023 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 7/31/2023 Approved ENRIQUE MIRELES
Gas Test 8/7/2023 No Access for Inspection SABAS ALONSO
Gas Test 8/10/2023 Approved SABAS ALONSO
Final 12/26/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 3/15/2024 Approved SABAS ALONSO
Final 3/15/2024 Corrections Issued SABAS ALONSO
HVAC-Final 3/15/2024 Approved SABAS ALONSO
PLUMBING-Final 3/15/2024 Approved SABAS ALONSO
Service/Power Release 3/15/2024 Not Ready for Inspection SABAS ALONSO
Special/Order Compliance 3/15/2024 Not Ready for Inspection SABAS ALONSO
Final 4/1/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 4/1/2024 Approved SABAS ALONSO