4114 S MARCASEL AVE 90066

Certificate Information: 4114 S MARCASEL AVE 90066

Application / Permit
21010-10000-01056
Plan Check / Job No.
B21LA03976
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT LAMC 12.22.A.33(c)-(d)
Permit Issued
Issued on 11/24/2021
Issuing Office
Current Status
CofO Issued on 4/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 DANIEL YIP
Corrections Issued 5/17/2021 DANIEL YIP
Quality Review Completed 5/20/2021 JASON HEALEY
Applicant returned to address corrections 10/1/2021 DANIEL YIP
Applicant returned to address corrections 10/28/2021 DANIEL YIP
Plan Check Approved 11/23/2021 DANIEL YIP
Issued 11/24/2021 APPLICANT
Building Plans Picked Up 12/7/2021 APPLICANT
CofO in Progress 4/20/2024 RICHARD STEINBACH
Permit Finaled 4/22/2024 DANIEL ORRANTE
CofO Issued 4/22/2024 DANIEL ORRANTE
Permit Finaled 4/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/7/2021 HISASHI KOBAYAKAWA
Permit Cleared 6/7/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 6/9/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/9/2021 HISASHI KOBAYAKAWA
Specific Plan Cleared 6/22/2021 PEDRO AYALA
Construction near power lines Cleared 9/13/2021 OSCAR CASTRO
Hydrant and Access approval Cleared 9/16/2021 GILBERT URREA
Roof/Waste drainage to street Cleared 11/2/2021 HISASHI KOBAYAKAWA
Hold Cleared 12/7/2021 JASON SHEETS

Contact Information

Contractor Mikhail Designs; Lic. No.: 960313-B 4335 MARINA CITY DRIVE #946      MARINA DEL REY, CA 90292
Engineer Martinez,, Michael Anthony; Lic. No.: S3825 902 15TH PLACE      HERMOSA BEACH, CA 90254

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/21/2022 Partial Inspection PATRICK QUALEY
Excavation/Setback/Form/Re-Bar 5/16/2022 Partial Inspection PATRICK QUALEY
PLUMBING-Rough 5/16/2022 Partial Approval PATRICK QUALEY
Footing/Foundation/Slab 6/7/2022 Approved PATRICK QUALEY
ELECTRICAL-Rough 10/20/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/20/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 10/20/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 10/20/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/28/2022 Approved JESUS RODRIGUEZ
Insulation 11/9/2022 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 11/10/2022 Approved JESUS RODRIGUEZ
Green Building Rough 11/10/2022 Approved JESUS RODRIGUEZ
Insulation 11/10/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 11/10/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 11/22/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/14/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/14/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 12/14/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/16/2023 Approved JESUS RODRIGUEZ
Final 10/16/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 10/16/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 10/16/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 10/16/2023 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 10/16/2023 Not Ready for Inspection JESUS RODRIGUEZ
Smoke Detectors 10/16/2023 Not Ready for Inspection JESUS RODRIGUEZ
Final 2/15/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 2/15/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 2/15/2024 Not Ready for Inspection JESUS RODRIGUEZ
Service/Power Release 2/26/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 4/16/2024 Approved JESUS RODRIGUEZ
Final 4/16/2024 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 4/16/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/16/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 4/16/2024 Approved JESUS RODRIGUEZ