11824 W OCEAN PARK BLVD 90064

Certificate Information: 11824 W OCEAN PARK BLVD 90064

Application / Permit
21010-10000-01053
Plan Check / Job No.
B21LA03938
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (1) DETACHED ADU PER GOVT CODE 65852.2(E)(1) “The LID clearancehas been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 1/24/2022
Issuing Office
Current Status
Issued on 1/24/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/12/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 CARLOS MONTES
Corrections Issued 4/20/2021 CARLOS MONTES
Quality Review Completed 4/27/2021 WING SUEN
Building Plans Picked Up 4/28/2021 APPLICANT
Applicant returned to address corrections 11/17/2021 CARLOS MONTES
Applicant returned to address corrections 12/15/2021 CARLOS MONTES
Plan Check Approved 1/24/2022 CARLOS MONTES
Issued 1/24/2022 APPLICANT
Green Plans Picked Up 3/16/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/4/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/13/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/13/2021 HISASHI KOBAYAKAWA
Miscellaneous Cleared 5/26/2021 LOUIS ORTEGA
Hydrant and Access approval Cleared 6/21/2021 KURT CORRAL
Specific Plan Cleared 7/6/2021 KEVIN ARUCAN
Roof/Waste drainage to street Cleared 1/2/2022 DENNIS BRAGIN
Miscellaneous Cleared 1/4/2022 RAYMOND MUGAMBWA

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Drake Michael Construction; Lic. No.: 531663-B 515 N CALERA STREET      GLENDORA, CA 91741
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/22/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 3/30/2022 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 4/1/2022 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 4/4/2022 Approved EVAN COOPER
Footing/Foundation/Slab 4/4/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 5/4/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 7/6/2022 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 7/13/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/13/2022 Approved JOHNNY MIRANDA
Green Building Rough 7/13/2022 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 7/13/2022 Approved JOHNNY MIRANDA
Insulation 7/25/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 7/25/2022 Partial Approval JOHNNY MIRANDA
Special/Order Compliance 7/25/2022 Corrections Issued JOHNNY MIRANDA
Drywall Nailing 8/1/2022 Partial Approval OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Not Ready WILBER ROSALES