18517 W CELTIC ST 91326
Certificate Information: 18517 W CELTIC ST 91326
- Application / Permit
- 21010-10000-01050
- Plan Check / Job No.
- B21LA03913
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached, 2-story Accessory Dwelling Unit with attached garage.
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | JOE VO |
| Corrections Issued | 3/28/2021 | JOE VO |
| Quality Review Completed | 3/30/2021 | MICHAEL PEREZ |
| Plan Check Approved | 8/4/2021 | JOE VO |
| No Progress | 8/19/2021 | JOE VO |
| Plan Check Approved | 8/19/2021 | JOE VO |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 9/4/2022 | JEFFREY PARD |
| Permit Finaled | 4/12/2023 | JOHN JANSON |
| CofO Issued | 4/12/2023 | JOHN JANSON |
| Permit Finaled | 4/12/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/6/2021 | GUILLERMO PETRA |
| Address approval | Cleared | 4/13/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 5/14/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/17/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/21/2021 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 8/19/2021 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/14/2021 | Partial Approval | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 9/16/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 9/16/2021 | Approved | JEFFREY PARD |
| Wood Frame | 10/4/2021 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 11/30/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 11/30/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 11/30/2021 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 12/7/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 12/7/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 12/15/2021 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 12/23/2021 | Approved | SEAN HAUPT |
| Drywall Nailing | 12/30/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/30/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 1/28/2022 | Approved | JEFFREY PARD |
| Sewer | 3/2/2022 | Approved | JEFFREY PARD |
| Underground Mechanical | 3/2/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 7/26/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 7/26/2022 | Approved | JEFFREY PARD |
| Final | 7/26/2022 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 7/26/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 7/26/2022 | Approved | JEFFREY PARD |
| PLUMBING-Final | 7/26/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 7/26/2022 | Approved | JEFFREY PARD |
| Smoke Detectors | 7/26/2022 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 7/26/2022 | Approved | JEFFREY PARD |
| Final | 9/6/2022 | OK to Issue CofO | JEFFREY PARD |
| Special/Order Compliance | 9/14/2022 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Final | 12/30/2022 | Approved | DAVID SCANTLIN |
| HVAC-Final | 12/30/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 12/30/2022 | Approved | DAVID SCANTLIN |