4543 1/4 W PICKFORD ST 90019

Certificate Information: 4543 1/4 W PICKFORD ST 90019

Application / Permit
21010-10000-01027
Plan Check / Job No.
B21LA03828
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY (2) ATTACHED ADU AT REAR OF LOT.
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
CofO Issued on 10/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 JOE VO
Corrections Issued 3/10/2021 JOE VO
Quality Review Completed 3/18/2021 MICHAEL PEREZ
Plan Check Approved 8/18/2021 JOE VO
Issued 8/31/2021 APPLICANT
CofO in Progress 9/30/2022 STUART CHAPMAN
Permit Finaled 10/13/2022 DEROLD HAUFF
CofO Issued 10/13/2022 DEROLD HAUFF
Permit Finaled 10/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/1/2021 MATTHEW CRAIG
Address approval Cleared 4/5/2021 CECILIO NAVARRO
Sewer availability Cleared 4/5/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/6/2021 CECILIO NAVARRO
Low Impact Development Cleared 8/4/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/11/2021 STEVE MELGAR

Contact Information

Contractor Affordable Building Solutions Inc; Lic. No.: 1068574-B 8885 SANDALWOOD CT      RANCHO CUCAMONGA, CA 91730

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 9/16/2021 Approved STUART CHAPMAN
METHANE-Barrier 9/16/2021 Approved STUART CHAPMAN
METHANE-Subgrade 9/16/2021 Approved STUART CHAPMAN
Piling/Pier/Caisson 9/16/2021 Approved STUART CHAPMAN
Pre-Inspection 9/16/2021 Approved STUART CHAPMAN
PLUMBING-Rough 9/25/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 9/27/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Approved STUART CHAPMAN
Insulation 9/30/2021 Partial Approval STUART CHAPMAN
METHANE-Rough 9/30/2021 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 9/30/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 10/19/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2021 Partial Approval STUART CHAPMAN
HVAC-Rough 10/19/2021 Approved STUART CHAPMAN
METHANE-Rough 10/19/2021 Approved STUART CHAPMAN
PLUMBING-Rough 10/19/2021 Approved STUART CHAPMAN
Shower Pan 10/19/2021 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 10/19/2021 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 11/8/2021 Partial Approval STUART CHAPMAN
Insulation 11/17/2021 Corrections Issued STUART CHAPMAN
Drywall Nailing 12/21/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 9/8/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 9/8/2022 Approved STUART CHAPMAN
Final 9/8/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 9/8/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 9/8/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 9/8/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 9/8/2022 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 9/8/2022 Approved STUART CHAPMAN
Final 9/29/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 9/29/2022 Approved STUART CHAPMAN
Service/Power Release 9/29/2022 Approved STUART CHAPMAN
Smoke Detectors 9/29/2022 Approved STUART CHAPMAN