747 W 104TH PL 90044

Certificate Information: 747 W 104TH PL 90044

Application / Permit
21010-10000-00991
Plan Check / Job No.
B21LA03774
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) Detached two car garage 400sf at the rear of property
Permit Issued
Issued on 6/16/2021
Issuing Office
Metro
Current Status
CofO Issued on 3/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 RAMA DABADGE
Corrections Issued 3/22/2021 RAMA DABADGE
Plan Check Approved 5/10/2021 RICARDO RAMIREZ
Issued 6/16/2021 APPLICANT
Building Plans Picked Up 6/21/2021 APPLICANT
CofO in Progress 3/7/2024 JAMES CHAVEZ
Permit Finaled 3/7/2024 ANSON MAGLASANG
CofO Issued 3/7/2024 ANSON MAGLASANG
Permit Finaled 3/7/2024 ANSON MAGLASANG

Permit Application Clearance Information

Construction near power lines Cleared 4/12/2021 TINA MIRANDA
Roof/Waste drainage to street Cleared 4/29/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/30/2021 CELINA MORENO

Contact Information

Contractor Solis Carlos; Lic. No.: 732102-B 1147 E 91ST ST      LOS ANGELES, CA 90002
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/16/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/20/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/23/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/12/2021 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 8/18/2021 Approved CRAIG DAVIS
BUILDING-Rough-Frame 9/1/2021 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 9/1/2021 Approved EUGENE CASSIDY
Wood Frame 9/1/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 9/24/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Approved EUGENE CASSIDY
Wood Frame 9/24/2021 Approved EUGENE CASSIDY
Insulation 9/28/2021 Corrections Issued EUGENE CASSIDY
Drywall Nailing 10/5/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/5/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 2/17/2022 Approved ANSON MAGLASANG
ELECTRICAL-Final 2/17/2022 Approved ANSON MAGLASANG
Final 2/17/2022 Corrections Issued ANSON MAGLASANG
Green Building Final 2/17/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Not Required ANSON MAGLASANG
Smoke Detectors 2/17/2022 Approved ANSON MAGLASANG
Final 11/7/2022 Not Ready for Inspection JOHN KLARIN
Final 12/19/2022 Partial Inspection JAMES CHAVEZ
Final 3/6/2024 OK to Issue CofO JAMES CHAVEZ