747 W 104TH PL 90044
Certificate Information: 747 W 104TH PL 90044
- Application / Permit
- 21010-10000-00991
- Plan Check / Job No.
- B21LA03774
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) Detached two car garage 400sf at the rear of property
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | RAMA DABADGE |
| Corrections Issued | 3/22/2021 | RAMA DABADGE |
| Plan Check Approved | 5/10/2021 | RICARDO RAMIREZ |
| Issued | 6/16/2021 | APPLICANT |
| Building Plans Picked Up | 6/21/2021 | APPLICANT |
| CofO in Progress | 3/7/2024 | JAMES CHAVEZ |
| Permit Finaled | 3/7/2024 | ANSON MAGLASANG |
| CofO Issued | 3/7/2024 | ANSON MAGLASANG |
| Permit Finaled | 3/7/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/12/2021 | TINA MIRANDA |
| Roof/Waste drainage to street | Cleared | 4/29/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2021 | CELINA MORENO |
Contact Information
| Contractor | Solis Carlos; Lic. No.: 732102-B | 1147 E 91ST ST LOS ANGELES, CA 90002 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/16/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/20/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/23/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/12/2021 | Approved | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 8/18/2021 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 9/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 9/1/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 9/1/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/24/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 9/24/2021 | Approved | EUGENE CASSIDY |
| Insulation | 9/28/2021 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 10/5/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/5/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 2/17/2022 | Approved | ANSON MAGLASANG |
| Final | 2/17/2022 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 2/17/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 2/17/2022 | SGSOV Not Required | ANSON MAGLASANG |
| Smoke Detectors | 2/17/2022 | Approved | ANSON MAGLASANG |
| Final | 11/7/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 12/19/2022 | Partial Inspection | JAMES CHAVEZ |
| Final | 3/6/2024 | OK to Issue CofO | JAMES CHAVEZ |