4513 E YELLOWSTONE ST 90032

Certificate Information: 4513 E YELLOWSTONE ST 90032

Application / Permit
21010-10000-00977
Plan Check / Job No.
B21LA03700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER 12.22.A.33
Permit Issued
Issued on 4/19/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 DANIEL YIP
Corrections Issued 3/8/2021 DANIEL YIP
Quality Review Completed 3/16/2021 JASON HEALEY
Applicant returned to address corrections 3/25/2021 DANIEL YIP
Applicant returned to address corrections 6/28/2021 DANIEL YIP
Plan Check Approved 9/14/2021 DANIEL YIP
Building Plans Picked Up 12/30/2022 APPLICANT
Plan Check Approved 4/18/2023 DANIEL YIP
Issued 4/19/2023 APPLICANT
CofO in Progress 2/21/2024 LILIANA PORTILLO
CofO Issued 2/28/2024 DEROLD HAUFF
Permit Finaled 2/28/2024 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/22/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 3/22/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 3/22/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 3/22/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 3/22/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 3/30/2021 RENZ SORIANO
Address approval Cleared 3/31/2021 RENZ SORIANO
Sewer availability Cleared 4/1/2021 RENZ SORIANO
Construction near power lines Cleared 5/21/2021 RIDWAN HARDY
GPI Written Notices Cleared 5/26/2021 DANIEL YIP
Grading Pre-Inspection Cleared 5/26/2021 DANIEL YIP
"D" conditions Cleared 5/27/2021 DANIEL CORONADO
"Q" conditions Cleared 5/27/2021 DANIEL CORONADO
ZI Cleared 5/27/2021 DANIEL CORONADO
Low Impact Development Cleared 8/27/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/30/2021 RENZ SORIANO

Contact Information

Contractor Sire Energy Inc; Lic. No.: 1027415-B 21054 SHERMAN WAY #325      CANOGA PARK, CA 91303
Engineer Baxter,, David Merrill; Lic. No.: S6332 380 BUCKSKIN LN      NORCO, CA 92860
Engineer Martinez,, Ron Edward; Lic. No.: L7383 P BOX 1382      DUARTE, CA 91009
Engineer Rooks,, Bret H; Lic. No.: C63445 174 LOMA BONITA      SAN LUIS OBISPO, CA 93401
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/24/2023 Partial Inspection AMY COLIN
Underground Mechanical 5/24/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 6/20/2023 Corrections Issued AMY COLIN
Underground Mechanical 6/20/2023 Approved AMY COLIN
Excavation/Setback/Form/Re-Bar 6/29/2023 Partial Inspection AMY COLIN
BUILDING-Rough-Frame 8/3/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 8/3/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Not Ready for Inspection AMY COLIN
Green Building Rough 8/3/2023 Not Ready for Inspection AMY COLIN
HVAC-Rough 8/3/2023 Corrections Issued AMY COLIN
PLUMBING-Rough 8/3/2023 Approved AMY COLIN
Verify Sprinkler Sign Off 8/3/2023 Approved AMY COLIN
BUILDING-Rough-Frame 8/15/2023 Approved AMY COLIN
HVAC-Rough 8/15/2023 Approved AMY COLIN
Shower Pan 8/15/2023 Approved AMY COLIN
Insulation 8/17/2023 Corrections Issued AMY COLIN
Insulation 8/22/2023 Approved AMY COLIN
Interior/Exterior Lathing 8/22/2023 Not Ready for Inspection AMY COLIN
Drywall Nailing 9/11/2023 Approved AMY COLIN
Green Building Rough 9/11/2023 Approved AMY COLIN
Interior/Exterior Lathing 9/11/2023 Not Ready for Inspection AMY COLIN
Interior/Exterior Lathing 9/25/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 10/23/2023 Approved AMY COLIN
Rough-Elec/Plmb/HVAC 12/8/2023 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Not Ready AMY COLIN
ELECTRICAL-Final 1/5/2024 Approved AMY COLIN
Final 1/5/2024 Corrections Issued AMY COLIN
HVAC-Final 1/5/2024 Approved AMY COLIN
PLUMBING-Final 1/5/2024 Approved AMY COLIN
Service/Power Release 1/5/2024 Approved AMY COLIN
Final 2/20/2024 OK to Issue CofO LILIANA PORTILLO
Footing/Foundation/Slab 2/20/2024 Approved LILIANA PORTILLO
Green Building Final 2/20/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Not Required LILIANA PORTILLO
Smoke Detectors 2/20/2024 Approved LILIANA PORTILLO