4513 E YELLOWSTONE ST 90032
Certificate Information: 4513 E YELLOWSTONE ST 90032
- Application / Permit
- 21010-10000-00977
- Plan Check / Job No.
- B21LA03700
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER 12.22.A.33
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | DANIEL YIP |
| Corrections Issued | 3/8/2021 | DANIEL YIP |
| Quality Review Completed | 3/16/2021 | JASON HEALEY |
| Applicant returned to address corrections | 3/25/2021 | DANIEL YIP |
| Applicant returned to address corrections | 6/28/2021 | DANIEL YIP |
| Plan Check Approved | 9/14/2021 | DANIEL YIP |
| Building Plans Picked Up | 12/30/2022 | APPLICANT |
| Plan Check Approved | 4/18/2023 | DANIEL YIP |
| Issued | 4/19/2023 | APPLICANT |
| CofO in Progress | 2/21/2024 | LILIANA PORTILLO |
| CofO Issued | 2/28/2024 | DEROLD HAUFF |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/22/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 3/22/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 3/22/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 3/22/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 3/22/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | RENZ SORIANO |
| Address approval | Cleared | 3/31/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 4/1/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 5/21/2021 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 5/26/2021 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 5/26/2021 | DANIEL YIP |
| "D" conditions | Cleared | 5/27/2021 | DANIEL CORONADO |
| "Q" conditions | Cleared | 5/27/2021 | DANIEL CORONADO |
| ZI | Cleared | 5/27/2021 | DANIEL CORONADO |
| Low Impact Development | Cleared | 8/27/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/30/2021 | RENZ SORIANO |
Contact Information
| Contractor | Sire Energy Inc; Lic. No.: 1027415-B | 21054 SHERMAN WAY #325 CANOGA PARK, CA 91303 |
| Engineer | Baxter,, David Merrill; Lic. No.: S6332 | 380 BUCKSKIN LN NORCO, CA 92860 |
| Engineer | Martinez,, Ron Edward; Lic. No.: L7383 | P BOX 1382 DUARTE, CA 91009 |
| Engineer | Rooks,, Bret H; Lic. No.: C63445 | 174 LOMA BONITA SAN LUIS OBISPO, CA 93401 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/24/2023 | Partial Inspection | AMY COLIN |
| Underground Mechanical | 5/24/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 6/20/2023 | Corrections Issued | AMY COLIN |
| Underground Mechanical | 6/20/2023 | Approved | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Partial Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 8/3/2023 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Rough | 8/3/2023 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Not Ready for Inspection | AMY COLIN |
| Green Building Rough | 8/3/2023 | Not Ready for Inspection | AMY COLIN |
| HVAC-Rough | 8/3/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 8/3/2023 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 8/3/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 8/15/2023 | Approved | AMY COLIN |
| HVAC-Rough | 8/15/2023 | Approved | AMY COLIN |
| Shower Pan | 8/15/2023 | Approved | AMY COLIN |
| Insulation | 8/17/2023 | Corrections Issued | AMY COLIN |
| Insulation | 8/22/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 8/22/2023 | Not Ready for Inspection | AMY COLIN |
| Drywall Nailing | 9/11/2023 | Approved | AMY COLIN |
| Green Building Rough | 9/11/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/11/2023 | Not Ready for Inspection | AMY COLIN |
| Interior/Exterior Lathing | 9/25/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/23/2023 | Approved | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 12/8/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Not Ready | AMY COLIN |
| ELECTRICAL-Final | 1/5/2024 | Approved | AMY COLIN |
| Final | 1/5/2024 | Corrections Issued | AMY COLIN |
| HVAC-Final | 1/5/2024 | Approved | AMY COLIN |
| PLUMBING-Final | 1/5/2024 | Approved | AMY COLIN |
| Service/Power Release | 1/5/2024 | Approved | AMY COLIN |
| Final | 2/20/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/20/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 2/20/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Not Required | LILIANA PORTILLO |
| Smoke Detectors | 2/20/2024 | Approved | LILIANA PORTILLO |