3045 S CRENSHAW BLVD 90016

Certificate Information: 3045 S CRENSHAW BLVD 90016

Application / Permit
21010-10000-00966
Plan Check / Job No.
B21LA03600
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW 6-STORY, 168-UNIT (17 ELI = 10%) MIXED-USE BLDG TO INCLUDE A 4-STORY, TYPE IIIA, AFFORDABLE HOUSING APARTMENT OVER 1-STORY, TYPE IA, PARKING GARAGE OVER GROUND FLOOR, TYPE 1A, COMMERCIAL RETAIL OVER 1-LEVEL SUBTERRANEAN PARKING, TIER 3 TOC WITH ADDITIONAL INCENTIVES
Permit Issued
Issued on 4/20/2023
Issuing Office
Metro
Current Status
CofO Corrected on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 4/19/2023 KEVIN MORALES
Issued 4/20/2023 APPLICANT
CofO Issued-Status Void 12/31/2025 ERNESTO CORRAL
Permit Finaled-Status Void 12/31/2025 ERNESTO CORRAL
Re-Activate Permit 1/5/2026 ERNESTO CORRAL
Permit Finaled 1/9/2026 ERNESTO CORRAL
CofO Corrected 1/9/2026 ERNESTO CORRAL
Permit Finaled 1/9/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 4/19/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/23/2022 TREVOR QUAN
Trees in Parkway Cleared 6/11/2022 ADALBERTO VERA
Bicycle Parking Cleared 6/16/2022 JEREMY CHOK
Building over 36-ft Cleared 6/23/2022 CALOSHA APPROVED
Historic Resource Verification Cleared 7/7/2022 MAX LODER
Hydrant and Access approval Cleared 7/8/2022 JOHN CONNEALLY
Highway dedication Cleared 8/3/2022 TREVOR QUAN
Permit Cleared 8/3/2022 TREVOR QUAN
Green Code Cleared 9/20/2022 AARON COSTA
Fire Marshal Fire Life Safety Cleared 9/28/2022 WILLIAM JOHNS
DAS Clearance Cleared 10/5/2022 KEVIN MORALES
Low Impact Development Cleared 12/7/2022 ORVAL HERNANDEZ-MARCI
Miscellaneous Cleared 12/23/2022 JASON CHAN
Miscellaneous Cleared 12/23/2022 JASON CHAN
Opn space landscape/Water mgmt Cleared 12/23/2022 JASON CHAN
Roof/Waste drainage to street Cleared 12/23/2022 THAN WIN
Site Plan review Cleared 12/23/2022 JASON CHAN
Specific Plan Cleared 12/23/2022 JASON CHAN
Driveway location Cleared 12/24/2022 TAIMOUR TANAVOLI
Internal circulation Cleared 12/24/2022 TAIMOUR TANAVOLI
Density Bonus 12.22.A.31 Cleared 1/3/2023 MARITESS GO
Miscellaneous Cleared 1/3/2023 DAVID URITA
Redevelopment Project Area Cleared 1/3/2023 DAVID URITA
Sewer availability Cleared 3/31/2023 CHRISTOPHER ROCHA
Work Adjacent to Public Way Cleared 4/5/2023 JOSE RODRIGUEZ

Contact Information

Architect Mankar,, Abhijeet D; Lic. No.: C29368 3253 ROMULUS STREET      LOS ANGELES, CA 90065
Contractor Owner-Builder       ,
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Larocca,, Francis; Lic. No.: C75121 2008A BELMONT LANE      REDONDO BEACH, CA 90278

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/16/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/22/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/23/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/24/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/28/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/29/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/30/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/1/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/5/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/6/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/7/2023 Conditional Approval GREGORY POMISH
Deputy Shotcrete 9/7/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/8/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/8/2023 Partial Approval JAMES POWERS
Green Building Rough 9/8/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/8/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/8/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/11/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/11/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/12/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/12/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/13/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/13/2023 Partial Approval JAMES POWERS
Green Building Rough 9/13/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/13/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/13/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/14/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/14/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/14/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/15/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/15/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/18/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/18/2023 Partial Approval JAMES POWERS
Green Building Rough 9/18/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/18/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/18/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/19/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/19/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/20/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/20/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/20/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/21/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/21/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/22/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/22/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/25/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 9/26/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/26/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/26/2023 Partial Approval JAMES POWERS
Green Building Rough 9/26/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/26/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/26/2023 Not Ready for Inspection JAMES POWERS
Deputy Other (see comments) 9/27/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/27/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/27/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/27/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 9/28/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/28/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/28/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 9/29/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/29/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/29/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/3/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/4/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/5/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/10/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/11/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/11/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/12/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/13/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/16/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/17/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 10/17/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/18/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 10/18/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/19/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 10/19/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/19/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/20/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 10/20/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 10/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 10/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 10/25/2023 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 10/25/2023 Conditional Approval LARRY ARNICK
Deputy Shotcrete 10/25/2023 Conditional Approval LARRY ARNICK
Deputy Shotcrete 10/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 10/30/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/30/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 10/30/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/30/2023 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/30/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/31/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/31/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/1/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/3/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/7/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 11/8/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/8/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 11/9/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/9/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 11/13/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/13/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 11/13/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/13/2023 Not Ready for Inspection JAMES POWERS
Green Building Rough 11/13/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 11/13/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/13/2023 Not Ready for Inspection JAMES POWERS
Deputy Other (see comments) 11/14/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/14/2023 Partial Approval JAMES POWERS
Deputy Other (see comments) 11/15/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/15/2023 Partial Approval JAMES POWERS
Green Building Rough 11/17/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 11/17/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/17/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 11/20/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 11/20/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/21/2023 Conditional Approval LARRY ARNICK
Deputy Shotcrete 11/21/2023 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 11/21/2023 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 11/22/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 11/30/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 11/30/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/1/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/1/2023 Partial Approval JAMES POWERS
Green Building Rough 12/1/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/1/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/1/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/4/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/4/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/5/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/5/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/6/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/6/2023 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/7/2023 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/8/2023 Partial Approval JAMES POWERS
Green Building Rough 12/8/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/8/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/8/2023 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 12/11/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/11/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/11/2023 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/12/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/12/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/15/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/18/2023 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/22/2023 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/26/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/26/2023 Partial Approval JAMES POWERS
Protected Tree Letter 12/26/2023 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/27/2023 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/28/2023 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/2/2024 Partial Approval JAMES POWERS
Green Building Rough 1/2/2024 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/2/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/2/2024 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 1/3/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/4/2024 Partial Approval JAMES POWERS
Deputy Shotcrete 1/4/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/5/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/5/2024 Partial Approval JAMES POWERS
Deputy Shotcrete 1/5/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/5/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/8/2024 Partial Approval JAMES POWERS
Deputy Shotcrete 1/8/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/9/2024 Partial Approval JAMES POWERS
Deputy Shotcrete 1/9/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/10/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/11/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/11/2024 Partial Approval JAMES POWERS
Green Building Rough 1/18/2024 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/18/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 1/18/2024 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 1/19/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/19/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/23/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/24/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/24/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/25/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/26/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/2/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/2/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/9/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/12/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/13/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/14/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/15/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/16/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/20/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/21/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/21/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/22/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/22/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/23/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/26/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/26/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/27/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/27/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/28/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/28/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/28/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/28/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/29/2024 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/1/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/6/2024 Partial Approval JAMES POWERS
Deputy Shotcrete 3/6/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/6/2024 Partial Approval JAMES POWERS
Deputy Shotcrete 3/7/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/8/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/12/2024 Partial Approval JAMES POWERS
Green Building Rough 3/12/2024 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 3/12/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/12/2024 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 3/13/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/13/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/14/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/14/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/14/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/15/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/15/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/18/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/19/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/20/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/21/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/21/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/22/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/22/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/26/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/27/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/28/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/29/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/2/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/3/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/4/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/5/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/8/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/9/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/10/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/11/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/15/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/16/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/17/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/18/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 4/23/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/24/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/25/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/26/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/30/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/1/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/2/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/3/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/9/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/16/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval JAMES POWERS
Insulation 7/9/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 7/9/2024 Partial Approval JAMES POWERS
Insulation 7/12/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/29/2024 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Approval JAMES POWERS
Wood Frame 8/13/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/6/2024 Partial Approval JAMES POWERS
Insulation 10/9/2024 Partial Approval JAMES POWERS
Wood Frame 10/9/2024 Partial Approval JAMES POWERS
Insulation 10/11/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 10/11/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 10/11/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/17/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/23/2024 Not Ready for Inspection JAMES POWERS
Insulation 10/23/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/24/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/25/2024 Not Ready for Inspection JAMES POWERS
Insulation 10/25/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/5/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/6/2024 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 11/6/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/8/2024 Not Ready for Inspection JAMES POWERS
Insulation 11/8/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/8/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/13/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 11/13/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 11/13/2024 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 11/14/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 11/14/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 11/14/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/15/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 11/15/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/18/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 11/18/2024 Partial Inspection JEFFREY FULTON
Insulation 11/19/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/20/2024 Not Ready for Inspection LARRY ARNICK
Insulation 11/20/2024 Partial Approval LARRY ARNICK
Light Gage Steel Frame 11/20/2024 Not Ready for Inspection LARRY ARNICK
Insulation 11/25/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/25/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/26/2024 Partial Approval JAMES POWERS
Insulation 11/26/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 11/26/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 12/2/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/9/2024 Partial Approval NICK DANERI
Insulation 12/9/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 12/9/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 12/11/2024 Partial Approval JAMES POWERS
Special/Order Compliance 12/11/2024 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 12/18/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/31/2024 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 1/6/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/16/2025 Partial Approval JAMES POWERS
Insulation 1/16/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/17/2025 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 1/23/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/24/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 2/10/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/14/2025 Partial Approval JAMES POWERS
Special/Order Compliance 4/14/2025 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/16/2025 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/2/2025 Partial Approval LARRY ARNICK
Special/Order Compliance 5/12/2025 Conditional Approval LARRY ARNICK
Deputy Other (see comments) 8/20/2025 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/20/2025 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/20/2025 Partial Approval JAMES POWERS
Deputy Shotcrete 8/20/2025 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/20/2025 Partial Approval JAMES POWERS
Pre-Inspection 8/20/2025 Partial Approval JAMES POWERS
Final 8/27/2025 OK for TCO JAMES POWERS
Footing/Foundation/Slab 8/27/2025 Approved JAMES POWERS
Green Building Final 8/27/2025 Approved JAMES POWERS
Green Building Rough 8/27/2025 Approved JAMES POWERS
Reinforced Concrete Frame 8/27/2025 Approved JAMES POWERS
Reinforced Masonry Frame 8/27/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Approved JAMES POWERS
Smoke Detectors 8/27/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 8/27/2025 Approved JAMES POWERS
Final 10/2/2025 OK for TCO JAMES POWERS
Special/Order Compliance 11/12/2025 Partial Approval JAMES POWERS
Final 12/11/2025 OK for TCO JAMES POWERS
Final 12/18/2025 OK for TCO JAMES POWERS