11779 W GARBER ST 91342
Certificate Information: 11779 W GARBER ST 91342
- Application / Permit
- 21010-10000-00965
- Plan Check / Job No.
- B21LA03570
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached 2-Story ADU.
- Permit Issued
- Issued on 8/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | JOE VO |
| Corrections Issued | 3/27/2021 | JOE VO |
| Quality Review Completed | 3/30/2021 | MICHAEL PEREZ |
| Plan Check Approved | 7/23/2021 | JOE VO |
| Issued | 8/12/2021 | APPLICANT |
| CofO in Progress | 2/22/2023 | MICHEL ABAJAN |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/28/2021 | JOE VO |
| Address approval | Cleared | 4/9/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/9/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 5/21/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 6/24/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/29/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 7/8/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: NA43590 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/14/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 10/19/2021 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 10/20/2021 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 11/5/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/5/2021 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 11/12/2021 | Corrections Issued | MICHEL ABAJAN |
| Pre-Inspection | 1/18/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 2/18/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/10/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/10/2022 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Rough | 5/10/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 5/10/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/10/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 5/10/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/9/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 6/14/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/7/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/27/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/4/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/12/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 11/17/2022 | Approved | MICHEL ABAJAN |
| Final | 11/17/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/17/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/17/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 11/17/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/17/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 11/17/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 11/17/2022 | Approved | MICHEL ABAJAN |
| Final | 1/30/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/30/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/13/2023 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 2/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 2/22/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 2/22/2023 | Approved | MICHEL ABAJAN |