5529 W RED OAK DR 90068

Certificate Information: 5529 W RED OAK DR 90068

Application / Permit
21010-10000-00962
Plan Check / Job No.
B21LA03563
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE TO ACCESORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 4/1/2021
Issuing Office
Current Status
CofO Issued on 3/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/1/2021 KEVIN MORALES
Corrections Issued 3/1/2021 KEVIN MORALES
Plan Check Approved 3/29/2021 KEVIN MORALES
Issued 4/1/2021 APPLICANT
CofO in Progress 4/11/2022 RUBEN SALAS
Permit Finaled 3/20/2023 DANIEL ORRANTE
CofO Issued 3/20/2023 DANIEL ORRANTE
Permit Finaled 3/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/12/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/12/2021 CECILIO NAVARRO
Sewer availability Cleared 3/12/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 3/25/2021 PATRICK MISCHLICH

Contact Information

Contractor Mod Design Build; Lic. No.: 1031321-B PO BOX 65008      LOS ANGELES, CA 90065

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/13/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 7/14/2021 Partial Inspection RAUL BARAJAS
Deputy Drilled-In Anchors 7/26/2021 Conditional Approval ROBERT CORNELL
Footing/Foundation/Slab 8/3/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/5/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 8/5/2021 Partial Approval RAUL BARAJAS
Sewer 8/5/2021 Partial Approval RAUL BARAJAS
Underground Mechanical 8/5/2021 Partial Approval RAUL BARAJAS
Wood Frame 9/7/2021 Partial Approval ARTHUR SARGSYAN
BUILDING-Rough-Frame 10/29/2021 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 10/29/2021 Corrections Issued BRIAN SULLIVAN
Green Building Rough 10/29/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 10/29/2021 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 10/29/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 11/19/2021 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 11/19/2021 Approved BRIAN SULLIVAN
Green Building Rough 11/19/2021 Approved BRIAN SULLIVAN
HVAC-Rough 11/19/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 11/19/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 11/19/2021 Approved BRIAN SULLIVAN
Insulation 12/1/2021 Corrections Issued JOSEPH MCGARRY
Shower Pan 12/1/2021 Approved JOSEPH MCGARRY
Insulation 12/10/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 12/10/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 12/16/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 12/16/2021 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 1/31/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 3/18/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/18/2022 SGSOV Not Ready BRIAN SULLIVAN
ELECTRICAL-Final 4/8/2022 Approved RUBEN SALAS
Final 4/8/2022 OK to Issue CofO RUBEN SALAS
Green Building Final 4/8/2022 Approved RUBEN SALAS
HVAC-Final 4/8/2022 Approved RUBEN SALAS
PLUMBING-Final 4/8/2022 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Approved RUBEN SALAS
Smoke Detectors 4/8/2022 Approved RUBEN SALAS