2805-2805 1/2 S MAPLE AVE 90011
Certificate Information: 2805-2805 1/2 S MAPLE AVE 90011
- Application / Permit
- 21010-10000-00957
- Plan Check / Job No.
- B21LA03513
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* 2 (N) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) & (g)
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- CofO Issued on 11/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | LAMAR DAVIS |
| Corrections Issued | 3/31/2021 | LAMAR DAVIS |
| Quality Review Completed | 4/8/2021 | MINYE PAK |
| Applicant returned to address corrections | 6/9/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 6/24/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 4/20/2022 | LAMAR DAVIS |
| Plan Check Approved | 4/21/2022 | LAMAR DAVIS |
| Issued | 4/22/2022 | APPLICANT |
| CofO in Progress | 11/8/2023 | ALEJANDRO DE ARTOLA |
| CofO Issued | 11/17/2023 | DEROLD HAUFF |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 6/2/2021 | STEVE MELGAR |
| ZA Case | Cleared | 7/27/2021 | ANNA VIDAL |
| Address approval | Cleared | 8/3/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/4/2021 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 9/19/2021 | JOHN CONNEALLY |
| Tenant Habitability Plan | Cleared | 10/6/2021 | GABRIEL RETA |
| Miscellaneous | Cleared | 10/28/2021 | LAMAR DAVIS |
| Trees in Parkway | Cleared | 3/8/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 3/29/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 4/1/2022 | JEANETTE VONG |
Contact Information
| Architect | Haidar,, Aly Reda; Lic. No.: C22450 | 225 QUEEN STREET 8-F HONOLULU, HI 96813 |
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/27/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/7/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 7/7/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 7/7/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 7/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 7/15/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 7/15/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 7/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 7/27/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/30/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 8/30/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 10/24/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/24/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 10/26/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 11/1/2022 | Approved | JULIAN AMAYA |
| HVAC-Rough | 11/1/2022 | Approved | JULIAN AMAYA |
| PLUMBING-Rough | 11/1/2022 | Approved | JULIAN AMAYA |
| Wood Frame | 11/4/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 11/8/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 11/16/2022 | Approved | RYAN SALAZAR |
| Green Building Rough | 11/16/2022 | Approved | RYAN SALAZAR |
| Underground Mechanical | 2/2/2023 | Approved | BRENDAN MORELLI |
| Sewer | 2/13/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/20/2023 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Final | 8/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 8/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 9/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 9/27/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 9/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 10/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/8/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |