2805-2805 1/2 S MAPLE AVE 90011

Certificate Information: 2805-2805 1/2 S MAPLE AVE 90011

Application / Permit
21010-10000-00957
Plan Check / Job No.
B21LA03513
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* 2 (N) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) & (g)
Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 LAMAR DAVIS
Corrections Issued 3/31/2021 LAMAR DAVIS
Quality Review Completed 4/8/2021 MINYE PAK
Applicant returned to address corrections 6/9/2021 LAMAR DAVIS
Applicant returned to address corrections 6/24/2021 LAMAR DAVIS
Applicant returned to address corrections 4/20/2022 LAMAR DAVIS
Plan Check Approved 4/21/2022 LAMAR DAVIS
Issued 4/22/2022 APPLICANT
CofO in Progress 11/8/2023 ALEJANDRO DE ARTOLA
CofO Issued 11/17/2023 DEROLD HAUFF
Permit Finaled 11/17/2023 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 6/2/2021 STEVE MELGAR
ZA Case Cleared 7/27/2021 ANNA VIDAL
Address approval Cleared 8/3/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/4/2021 STEVE MELGAR
Sewer availability Cleared 8/4/2021 STEVE MELGAR
Hydrant and Access approval Cleared 9/19/2021 JOHN CONNEALLY
Tenant Habitability Plan Cleared 10/6/2021 GABRIEL RETA
Miscellaneous Cleared 10/28/2021 LAMAR DAVIS
Trees in Parkway Cleared 3/8/2022 ADALBERTO VERA
Low Impact Development Cleared 3/29/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/1/2022 JEANETTE VONG

Contact Information

Architect Haidar,, Aly Reda; Lic. No.: C22450 225 QUEEN STREET 8-F      HONOLULU, HI 96813
Contractor Owner-Builder       ,
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/27/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 7/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 7/7/2022 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 7/15/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/15/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 7/15/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 7/15/2022 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 7/27/2022 Corrections Issued JOAQUIN GREENOUGH
METHANE-Subgrade 7/27/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/30/2022 Approved ENRIQUE MIRELES
METHANE-Barrier 8/30/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 10/24/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 10/24/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Deputy Wood Construction 10/26/2022 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/1/2022 Approved JULIAN AMAYA
HVAC-Rough 11/1/2022 Approved JULIAN AMAYA
PLUMBING-Rough 11/1/2022 Approved JULIAN AMAYA
Wood Frame 11/4/2022 Approved ENRIQUE MIRELES
Insulation 11/8/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 11/16/2022 Approved RYAN SALAZAR
Green Building Rough 11/16/2022 Approved RYAN SALAZAR
Underground Mechanical 2/2/2023 Approved BRENDAN MORELLI
Sewer 2/13/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 6/20/2023 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 8/21/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/21/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/21/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/21/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 8/21/2023 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Final 8/21/2023 Approved ALEJANDRO DE ARTOLA
METHANE-Rough 8/21/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/21/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/21/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 8/21/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/21/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 8/21/2023 Approved ALEJANDRO DE ARTOLA
Final 9/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/27/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 9/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/4/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/4/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 10/4/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/4/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/4/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 10/4/2023 Approved ALEJANDRO DE ARTOLA
Final 10/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/8/2023 Approved ALEJANDRO DE ARTOLA
Final 11/8/2023 OK to Issue CofO ALEJANDRO DE ARTOLA