2059 W 99TH ST 90047

Certificate Information: 2059 W 99TH ST 90047

Application / Permit
21010-10000-00955
Plan Check / Job No.
B21LA03507
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 11/2/2021
Issuing Office
Current Status
CofO Issued on 1/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 DANIEL YIP
Corrections Issued 3/10/2021 DANIEL YIP
Quality Review Completed 3/16/2021 JASON HEALEY
Applicant returned to address corrections 6/11/2021 DANIEL YIP
Plan Check Approved 10/18/2021 DANIEL YIP
Issued 11/2/2021 APPLICANT
Building Plans Picked Up 11/5/2021 APPLICANT
CofO in Progress 12/27/2022 ENRIQUE MIRELES
Permit Finaled 1/3/2023 DEROLD HAUFF
CofO Issued 1/3/2023 DEROLD HAUFF
Permit Finaled 1/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/15/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 7/15/2021 THOMAS LANG
Sewer availability Cleared 7/15/2021 THOMAS LANG
Hydrant and Access approval Cleared 8/3/2021 ROBERT DUFF
Construction near power lines Cleared 9/16/2021 RIDWAN HARDY
Low Impact Development Cleared 10/5/2021 KHAING AYE
Roof/Waste drainage to street Cleared 10/8/2021 THAN WIN

Contact Information

Architect Williams,, Gregory Keith; Lic. No.: C22965 1216 N DETROIT STREET APT 5      WEST HOLLYWOOD, CA 90046
Contractor Owner-Builder       ,
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/6/2022 Approved ENRIQUE MIRELES
Deputy Methane Barrier 5/11/2022 Approved ENRIQUE MIRELES
Deputy Methane Barrier 5/12/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/2/2022 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 7/1/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Approved ENRIQUE MIRELES
Green Building Rough 7/1/2022 Approved ENRIQUE MIRELES
METHANE-Rough 7/1/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/1/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/7/2022 Approved ENRIQUE MIRELES
Insulation 7/19/2022 Approved ENRIQUE MIRELES
Drywall Nailing 8/2/2022 Approved ENRIQUE MIRELES
Service/Power Release 8/2/2022 Approved ENRIQUE MIRELES
Gas Test 8/5/2022 Approved ENRIQUE MIRELES
Final 9/9/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 9/9/2022 Approved ENRIQUE MIRELES
Green Building Final 9/9/2022 Approved ENRIQUE MIRELES
METHANE-Barrier 9/9/2022 Approved ENRIQUE MIRELES
METHANE-Subgrade 9/9/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 9/9/2022 Approved ENRIQUE MIRELES
Final 9/19/2022 Conditional Approval ENRIQUE MIRELES
Service/Power Release 9/22/2022 Approved ENRIQUE MIRELES
Final 11/2/2022 Conditional Approval ENRIQUE MIRELES