2059 W 99TH ST 90047
Certificate Information: 2059 W 99TH ST 90047
- Application / Permit
- 21010-10000-00955
- Plan Check / Job No.
- B21LA03507
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 1/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | DANIEL YIP |
| Corrections Issued | 3/10/2021 | DANIEL YIP |
| Quality Review Completed | 3/16/2021 | JASON HEALEY |
| Applicant returned to address corrections | 6/11/2021 | DANIEL YIP |
| Plan Check Approved | 10/18/2021 | DANIEL YIP |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| CofO in Progress | 12/27/2022 | ENRIQUE MIRELES |
| Permit Finaled | 1/3/2023 | DEROLD HAUFF |
| CofO Issued | 1/3/2023 | DEROLD HAUFF |
| Permit Finaled | 1/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2021 | THOMAS LANG |
| Sewer availability | Cleared | 7/15/2021 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 8/3/2021 | ROBERT DUFF |
| Construction near power lines | Cleared | 9/16/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/5/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 10/8/2021 | THAN WIN |
Contact Information
| Architect | Williams,, Gregory Keith; Lic. No.: C22965 | 1216 N DETROIT STREET APT 5 WEST HOLLYWOOD, CA 90046 |
| Contractor | Owner-Builder | , |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/6/2022 | Approved | ENRIQUE MIRELES |
| Deputy Methane Barrier | 5/11/2022 | Approved | ENRIQUE MIRELES |
| Deputy Methane Barrier | 5/12/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/2/2022 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/1/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 7/1/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 7/1/2022 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/1/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/7/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 7/19/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/2/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 8/2/2022 | Approved | ENRIQUE MIRELES |
| Gas Test | 8/5/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/9/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/9/2022 | Approved | ENRIQUE MIRELES |
| Green Building Final | 9/9/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 9/9/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 9/9/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/9/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/19/2022 | Conditional Approval | ENRIQUE MIRELES |
| Service/Power Release | 9/22/2022 | Approved | ENRIQUE MIRELES |
| Final | 11/2/2022 | Conditional Approval | ENRIQUE MIRELES |