18900 W PARTHENIA ST 1-64 91324

Certificate Information: 18900 W PARTHENIA ST 1-64 91324

Application / Permit
21010-10000-00932
Plan Check / Job No.
B21LA03430
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4-story, 64-unit (5 ELI, 3 VLI, 3 LI) affordable housing apartment building with 4 levels of Type IIIA apartments (and ground floor parking) over 1 level Type IA basement with parking utilizing TOC Tier 2 incentives.
Permit Issued
Issued on 4/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 3/2/2023 RODOLFO ARIAS
Issued 4/13/2023 APPLICANT
TCO Issued (Expire Date: 08-17-2026) 2/18/2026 RICKEY JACKSON
Permit Finaled 3/26/2026 RICKEY JACKSON
CofO Issued 3/26/2026 RICKEY JACKSON
Permit Finaled 3/26/2026 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 7/30/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/2/2021 LEE GUILBEAUX
Highway dedication Cleared 9/22/2021 LEE GUILBEAUX
Permit Cleared 9/22/2021 LEE GUILBEAUX
Driveway location Cleared 10/4/2021 SHEILA AHORAIAN
Low Impact Development Cleared 3/8/2022 ORVAL HERNANDEZ-MARCI
Miscellaneous Cleared 4/27/2022 JASON CHAN
Miscellaneous Cleared 4/27/2022 JASON CHAN
Miscellaneous Cleared 4/27/2022 JASON CHAN
Miscellaneous Cleared 4/27/2022 JASON CHAN
Site Plan review Cleared 4/27/2022 JASON CHAN
ZA Case Cleared 4/27/2022 JASON CHAN
Frnt yard landscape/Water mgmt Cleared 4/29/2022 JASON CHAN
Frnt yard landscape/Water mgmt Cleared 4/29/2022 JASON CHAN
Opn space landscape/Water mgmt Cleared 4/29/2022 JASON CHAN
Prkng lot landscape/Water mgmt Cleared 4/29/2022 JASON CHAN
Roof/Waste drainage to street Cleared 5/25/2022 DAGOVERTO GUERRERO
Green Code Cleared 5/26/2022 AARON COSTA
Bicycle Parking Cleared 5/27/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/6/2022 KURT CORRAL
Tenant Habitability Plan Cleared 7/6/2022 ISMAEL HERNANDEZ
Work Adjacent to Public Way Cleared 7/14/2022 LEE GUILBEAUX
Trees in Parkway Cleared 7/20/2022 ADALBERTO VERA
Density Bonus 12.22.A.31 Cleared 9/13/2022 JAMES MCCARTHY
Fire Marshal Fire Life Safety Cleared 10/19/2022 VIDAL GARCIA
Sewer availability Cleared 10/27/2022 COLIN LOREDO
DAS Clearance Cleared 12/8/2022 RODOLFO ARIAS
Building over 36-ft Cleared 2/23/2023 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 2/23/2023 CALOSHA APPROVED

Contact Information

Architect Fischer,, James Robert; Lic. No.: C32908 17904 HARTLAND STREET      RESEDA, CA 91335
Contractor Wilshire Construction L P; Lic. No.: 1048091-B 3470 WILSHIRE STE 500      LOS ANGELES, CA 90010
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254
Engineer Tang,, Stanley Siu Kei; Lic. No.: C56178 1105 N AVON STREET      BURBANK, CA 91505
Landscape Architect Kim,, Samuel Kyun; Lic. No.: LA3249 2669 SATURN ST      BREA, CA 92821

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/18/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/9/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 8/4/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/10/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 8/10/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/14/2023 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/14/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 8/15/2023 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 8/15/2023 Partial Inspection JEFFREY FULTON
Deputy Shotcrete 8/16/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 8/17/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 8/18/2023 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/23/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/24/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 8/24/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 8/24/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/25/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 8/25/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 8/25/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/28/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 8/28/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 8/28/2023 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/28/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/29/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 8/29/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 8/29/2023 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 8/29/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/30/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 8/30/2023 Conditional Approval JEFFREY FULTON
Deputy Shotcrete 8/30/2023 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 9/12/2023 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/12/2023 Corrections Issued JEFFREY FULTON
Deputy Reinf. Concrete 9/18/2023 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/18/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/19/2023 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/25/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/27/2023 Conditional Approval JEFFREY FULTON
Reinforced Concrete Frame 9/27/2023 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/28/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 9/29/2023 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 9/29/2023 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/6/2023 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 10/6/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 10/20/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 10/26/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 10/27/2023 Not Ready for Inspection JEFFREY FULTON
Insulation 10/30/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 11/30/2023 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/30/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 11/30/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/8/2023 Conditional Approval JEFFREY DURAN
Pre-Inspection 12/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/11/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 12/11/2023 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/12/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 12/12/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/13/2023 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 1/11/2024 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 1/17/2024 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Masonry 1/18/2024 Approved GRANT WOODS
Footing/Foundation/Slab 1/18/2024 Partial Approval GRANT WOODS
Green Building Rough 1/18/2024 Not Ready for Inspection GRANT WOODS
Verify Sprinkler Sign Off 1/18/2024 Not Ready for Inspection GRANT WOODS
Deputy Steel/Welding 1/26/2024 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 1/30/2024 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 1/30/2024 Not Ready for Inspection JEFFREY FULTON
Deputy Steel/Welding 1/31/2024 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 1/31/2024 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 2/8/2024 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 2/9/2024 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 2/13/2024 Conditional Approval JEFFREY FULTON
Special/Order Compliance 2/13/2024 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 2/14/2024 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 2/15/2024 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 2/16/2024 Conditional Approval JEFFREY FULTON
Insulation 2/16/2024 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 2/16/2024 Partial Inspection JEFFREY FULTON
Reinforced Masonry Frame 2/16/2024 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 2/20/2024 Corrections Issued JEFFREY FULTON
Deputy Steel/Welding 2/21/2024 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 2/22/2024 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 2/23/2024 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 2/27/2024 Approved JOHN KITCKO
Deputy Steel/Welding 2/28/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 2/28/2024 Partial Approval GREGORY POMISH
Deputy Steel/Welding 2/29/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/1/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/5/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/6/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/7/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 3/8/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/8/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 3/12/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 3/12/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/12/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 3/13/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 3/13/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/13/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 3/14/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 3/14/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/14/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 3/15/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/15/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 3/18/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/18/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 3/19/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/19/2024 Conditional Approval GREGORY POMISH
Reinforced Masonry Frame 3/19/2024 Partial Approval GREGORY POMISH
Deputy Fireproofing 3/20/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/20/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 3/21/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/21/2024 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 3/21/2024 Conditional Approval JEFFREY DURAN
Deputy Fireproofing 3/22/2024 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 3/22/2024 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 3/26/2024 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 3/27/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/28/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 3/29/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/1/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/1/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/2/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/2/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/3/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/3/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/4/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/4/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/5/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/5/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/8/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/8/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/9/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/9/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/10/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/10/2024 Conditional Approval GREGORY POMISH
Deputy Fireproofing 4/11/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/11/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/12/2024 Approved GREGORY POMISH
Deputy Steel/Welding 4/24/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 4/25/2024 Conditional Approval GREGORY POMISH
Deputy Steel/Welding 5/2/2024 Conditional Approval DEANDRE HOFFMAN
Deputy Steel/Welding 5/3/2024 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/6/2024 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 5/6/2024 Conditional Approval JEFFREY DURAN
Green Building Rough 5/7/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 5/7/2024 Not Ready for Inspection ROBERT DAVIS
Wood Frame 5/7/2024 Partial Approval ROBERT DAVIS
Deputy Steel/Welding 5/9/2024 Conditional Approval GREGORY POMISH
Deputy Wood Construction 5/17/2024 Conditional Approval GREGORY POMISH
Green Building Rough 5/17/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 5/17/2024 Not Ready for Inspection GREGORY POMISH
Wood Frame 5/17/2024 Partial Approval GREGORY POMISH
Deputy Steel/Welding 5/22/2024 Conditional Approval GREGORY POMISH
Deputy Wood Construction 6/5/2024 Conditional Approval GREGORY POMISH
Green Building Rough 6/5/2024 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 6/5/2024 Not Ready for Inspection GREGORY POMISH
Wood Frame 6/5/2024 Partial Inspection GREGORY POMISH
Deputy Steel/Welding 6/6/2024 Conditional Approval GREGORY POMISH
Green Building Rough 6/11/2024 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 6/11/2024 Not Ready for Inspection JEFFREY DURAN
Wood Frame 6/11/2024 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Partial Inspection GREGORY POMISH
Deputy Wood Construction 6/25/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Corrections Issued DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Inspection GREGORY POMISH
Green Building Rough 8/6/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 8/6/2024 Partial Inspection GREGORY POMISH
Wood Frame 8/6/2024 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 8/8/2024 Conditional Approval GREGORY POMISH
Green Building Rough 8/8/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 8/8/2024 Partial Inspection GREGORY POMISH
Wood Frame 8/8/2024 Partial Approval GREGORY POMISH
Insulation 8/12/2024 Partial Approval GREGORY POMISH
Deputy Wood Construction 8/14/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 8/16/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Not Ready for Inspection GREGORY POMISH
Deputy Wood Construction 8/20/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Partial Inspection GREGORY POMISH
Deputy Wood Construction 8/28/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Partial Approval GREGORY POMISH
Deputy Wood Construction 9/3/2024 Conditional Approval GREGORY POMISH
Deputy Wood Construction 9/5/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Partial Approval GREGORY POMISH
Deputy Wood Construction 9/6/2024 Conditional Approval GREGORY POMISH
Deputy Wood Construction 9/10/2024 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Inspection GREGORY POMISH
Insulation 9/25/2024 Not Ready for Inspection GREGORY POMISH
Insulation 10/15/2024 Partial Approval ROBERT DAVIS
Insulation 10/17/2024 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 10/21/2024 Partial Inspection GREGORY POMISH
Green Building Rough 10/21/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/21/2024 Partial Inspection GREGORY POMISH
Wood Frame 10/21/2024 Corrections Issued GREGORY POMISH
Insulation 10/23/2024 Partial Inspection GREGORY POMISH
Green Building Rough 10/25/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/25/2024 Partial Inspection GREGORY POMISH
Wood Frame 10/25/2024 Partial Inspection GREGORY POMISH
Green Building Rough 10/29/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/29/2024 Partial Inspection GREGORY POMISH
Wood Frame 10/29/2024 Partial Approval GREGORY POMISH
Insulation 10/31/2024 Partial Approval GREGORY POMISH
Insulation 11/4/2024 Partial Approval GREGORY POMISH
Insulation 11/6/2024 Partial Approval GREGORY POMISH
Deputy Drilled-In Anchors 11/7/2024 Conditional Approval GREGORY POMISH
Green Building Rough 11/8/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 11/8/2024 Partial Inspection GREGORY POMISH
Wood Frame 11/8/2024 Partial Inspection GREGORY POMISH
Drywall Nailing 11/14/2024 Partial Approval ROBERT DAVIS
Wood Frame 11/14/2024 Partial Approval ROBERT DAVIS
Insulation 11/26/2024 Partial Approval GREGORY POMISH
Insulation 11/27/2024 Partial Inspection GREGORY POMISH
Insulation 12/6/2024 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 12/10/2024 Partial Approval GREGORY POMISH
T-Bar Ceiling 12/11/2024 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 12/16/2024 Not Ready for Inspection GREGORY POMISH
Insulation 12/26/2024 Partial Approval GREGORY POMISH
T-Bar Ceiling 12/26/2024 Not Ready for Inspection GREGORY POMISH
Insulation 12/27/2024 Partial Approval GREGORY POMISH
Green Building Rough 12/30/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 12/30/2024 Partial Inspection GREGORY POMISH
Wood Frame 12/30/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 1/9/2025 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 1/10/2025 Partial Approval GREGORY POMISH
Drywall Nailing 1/14/2025 Partial Approval GREGORY POMISH
Green Building Rough 1/14/2025 Partial Inspection GREGORY POMISH
T-Bar Ceiling 1/23/2025 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 1/24/2025 Partial Inspection GREGORY POMISH
Green Building Rough 1/27/2025 Partial Inspection GREGORY POMISH
Insulation 2/10/2025 Partial Approval GREGORY POMISH
Drywall Nailing 3/3/2025 Partial Approval GREGORY POMISH
Green Building Rough 3/3/2025 Partial Inspection GREGORY POMISH
Insulation 3/5/2025 Partial Approval GREGORY POMISH
Drywall Nailing 3/14/2025 Partial Approval GREGORY POMISH
Green Building Rough 3/14/2025 Partial Inspection GREGORY POMISH
Insulation 3/25/2025 Partial Approval GREGORY POMISH
Insulation 3/28/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 4/3/2025 Partial Approval GREGORY POMISH
Green Building Rough 4/3/2025 Partial Inspection GREGORY POMISH
Drywall Nailing 4/8/2025 Partial Approval GREGORY POMISH
Green Building Rough 4/8/2025 Partial Inspection GREGORY POMISH
Insulation 4/11/2025 Partial Approval GREGORY POMISH
Insulation 4/15/2025 Partial Approval GREGORY POMISH
Green Building Rough 4/24/2025 Not Ready for Inspection GREGORY POMISH
T-Bar Ceiling 5/2/2025 Off-Hour Fees Due
Drywall Nailing 5/8/2025 Partial Approval GREGORY POMISH
Green Building Rough 5/8/2025 Partial Inspection GREGORY POMISH
Drywall Nailing 6/2/2025 Partial Approval GREGORY POMISH
Green Building Rough 6/2/2025 Partial Inspection GREGORY POMISH
Interior/Exterior Lathing 6/5/2025 Approved GREGORY POMISH
Drywall Nailing 6/20/2025 Partial Inspection ROBERT DAVIS
Green Building Rough 6/20/2025 Approved ROBERT DAVIS
Drywall Nailing 7/10/2025 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 7/31/2025 Not Ready for Inspection GREGORY POMISH
Wood Frame 7/31/2025 Partial Approval GREGORY POMISH
Drywall Nailing 8/27/2025 Partial Approval GREGORY POMISH
Light Gage Steel Frame 8/27/2025 Partial Approval GREGORY POMISH
Light Gage Steel Frame 9/5/2025 Not Ready for Inspection JOHN KITCKO
Insulation 10/22/2025 Approved GREGORY POMISH
Drywall Nailing 1/9/2026 Approved GREGORY POMISH
Final 1/9/2026 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 1/9/2026 Approved GREGORY POMISH
Green Building Final 1/9/2026 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 1/9/2026 Partial Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 1/9/2026 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 1/9/2026 Partial Inspection GREGORY POMISH
Wood Frame 1/9/2026 Partial Inspection GREGORY POMISH
Final 2/12/2026 Corrections Issued JOHN KITCKO
Green Building Final 2/12/2026 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 2/12/2026 Partial Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Approved JOHN KITCKO
Smoke Detectors 2/12/2026 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 2/12/2026 Not Ready for Inspection JOHN KITCKO
Wood Frame 2/12/2026 Partial Inspection JOHN KITCKO
Final 2/18/2026 OK for TCO GREGORY POMISH
Green Building Final 2/18/2026 Approved GREGORY POMISH
Reinforced Concrete Frame 2/18/2026 Approved GREGORY POMISH
Smoke Detectors 2/18/2026 Approved GREGORY POMISH
Verify Sprinkler Sign Off 2/18/2026 Approved GREGORY POMISH
Wood Frame 2/18/2026 Approved GREGORY POMISH