15947 W LEADWELL ST 91406

Certificate Information: 15947 W LEADWELL ST 91406

Application / Permit
21010-10000-00930
Plan Check / Job No.
B21LA03427
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: PROPOSED 2 STORY DETACHED ACCESSORY DWELLING UNIT (ADU) PER ORDINANCE.
Permit Issued
Issued on 3/4/2022
Issuing Office
Current Status
CofO Issued on 6/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 MICHAEL LOPEZ
Corrections Issued 3/25/2021 MICHAEL LOPEZ
Quality Review Completed 4/6/2021 WING SUEN
Applicant returned to address corrections 11/17/2021 MICHAEL LOPEZ
Applicant returned to address corrections 1/28/2022 MICHAEL LOPEZ
Plan Check Approved 2/18/2022 MICHAEL LOPEZ
Issued 3/4/2022 APPLICANT
CofO in Progress 5/31/2024 RAUL OLAGI
Permit Finaled 6/25/2024 RUBEN SALAS
CofO Issued 6/25/2024 RUBEN SALAS
Permit Finaled 6/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/23/2021 GUILLERMO PETRA
Construction near power lines Cleared 7/21/2021 RIDWAN HARDY
Construction within easement Cleared 7/21/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/16/2021 ABDULLAH SADOZAI
Sewer availability Cleared 8/16/2021 ABDULLAH SADOZAI
Low Impact Development Cleared 8/20/2021 SARAH YOUSSEF
Hydrant and Access approval Cleared 10/3/2021 KURT CORRAL
Roof/Waste drainage to street Cleared 10/18/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 3/6/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 3/24/2023 Not Ready for Inspection RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/4/2023 Approved RAUL OLAGI
PLUMBING-Rough 4/18/2023 Corrections Issued RAUL OLAGI
Wood Frame 4/18/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 4/28/2023 Partial Approval RAUL OLAGI
Wood Frame 4/28/2023 Partial Approval RAUL OLAGI
Insulation 5/3/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/26/2023 Approved RAUL OLAGI
Sewer 6/26/2023 Approved RAUL OLAGI
Underground Mechanical 6/26/2023 Approved RAUL OLAGI
Deputy Wood Construction 8/7/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/10/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 8/10/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval RAUL OLAGI
HVAC-Rough 8/10/2023 Approved RAUL OLAGI
PLUMBING-Rough 8/10/2023 Approved RAUL OLAGI
Verify Sprinkler Sign Off 8/10/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/18/2023 Approved RAUL OLAGI
Green Building Rough 8/18/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 8/24/2023 Partial Approval RAUL OLAGI
Insulation 9/13/2023 Corrections Issued RAUL OLAGI
Shower Pan 9/13/2023 Approved RAUL OLAGI
Insulation 9/21/2023 Approved RAUL OLAGI
Drywall Nailing 10/2/2023 Approved RAUL OLAGI
Underground Mechanical 10/2/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 10/12/2023 Approved RAUL OLAGI
Final 4/15/2024 Corrections Issued RAUL OLAGI
Green Building Final 4/15/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/15/2024 Approved RAUL OLAGI
Final 5/30/2024 OK to Issue CofO RAUL OLAGI
Service/Power Release 5/30/2024 Approved RAUL OLAGI