2702-2704 S ARLINGTON AVE 90018

Certificate Information: 2702-2704 S ARLINGTON AVE 90018

Application / Permit
21010-10000-00893
Plan Check / Job No.
B21LA03216
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-UNIT ACCESSORY DWELLING UNIT BUILDING ON THE REAR OF SITE, CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). **See comments**
Permit Issued
Issued on 1/5/2022
Issuing Office
Current Status
CofO Corrected on 8/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 JOHNNY WU
Corrections Issued 3/18/2021 JOHNNY WU
Quality Review Completed 3/18/2021 FARUK SEZER
Applicant returned to address corrections 10/22/2021 JOHNNY WU
Applicant returned to address corrections 12/3/2021 JOHNNY WU
Plan Check Approved 12/29/2021 JOHNNY WU
Issued 1/5/2022 APPLICANT
Building Plans Picked Up 1/13/2022 APPLICANT
CofO in Progress 7/13/2023 SABAS ALONSO
CofO Issued-Status Void 7/20/2023 DEROLD HAUFF
Permit Finaled-Status Void 7/20/2023 DEROLD HAUFF
Re-Activate Permit 7/25/2023 DEROLD HAUFF
CofO Corrected 8/11/2023 DEROLD HAUFF
Permit Finaled 8/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/5/2021 CECILIO NAVARRO
HPOZ Cleared 4/23/2021 MAX LODER
Eng Process Fee Ord 176,300 Cleared 5/7/2021 CECILIO NAVARRO
Highway dedication Cleared 8/13/2021 CECILIO NAVARRO
Sewer availability Cleared 9/23/2021 WALLIE JONG
Low Impact Development Cleared 9/24/2021 TA ANH
Roof/Waste drainage to street Cleared 10/1/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 10/6/2021 MATTHEW CRAIG
Green Code Cleared 12/2/2021 JOHNNY WU

Contact Information

Architect Kim,, Nam H; Lic. No.: C30825 1832 SANTA RENA DRIVE      RANCHO PALOS VERDES, CA 90275
Contractor Valencia Construction Company; Lic. No.: 1015167-B 12069 SMALLWOOD AVE      DOWNEY, CA 90242
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/15/2022 Approved JOAQUIN GREENOUGH
METHANE-Barrier 2/15/2022 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 2/15/2022 Approved JOAQUIN GREENOUGH
Service/Power Release 2/15/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 3/18/2022 Partial Approval SABAS ALONSO
Wood Frame 3/18/2022 Partial Approval SABAS ALONSO
Insulation 3/23/2022 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Approved SABAS ALONSO
Wood Frame 3/31/2022 Partial Approval SABAS ALONSO
PLUMBING-Rough 5/24/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 7/11/2022 Not Ready for Inspection HORACE FULTZ
Green Building Rough 7/11/2022 Approved HORACE FULTZ
MERV13>=Rough 7/11/2022 Approved HORACE FULTZ
METHANE-Rough 7/11/2022 Approved HORACE FULTZ
Verify Sprinkler Sign Off 7/11/2022 Approved HORACE FULTZ
Wood Frame 7/11/2022 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 8/9/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 8/9/2022 Approved SABAS ALONSO
Green Building Rough 8/9/2022 Approved SABAS ALONSO
HVAC-Rough 8/9/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 8/9/2022 Partial Approval SABAS ALONSO
Insulation 8/12/2022 Approved SABAS ALONSO
Drywall Nailing 8/25/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 11/10/2022 Approved SABAS ALONSO
Sewer 1/25/2023 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 1/27/2023 Partial Approval SABAS ALONSO
Sewer 1/31/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 2/10/2023 Not Ready for Inspection RAUL BARAJAS
Gas Test 2/10/2023 Not Ready for Inspection RAUL BARAJAS
Final 2/23/2023 Corrections Issued SABAS ALONSO
Green Building Final 2/23/2023 Approved SABAS ALONSO
MERV13>=Final 2/23/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Not Ready SABAS ALONSO
Service/Power Release 2/23/2023 Approved SABAS ALONSO
Smoke Detectors 2/23/2023 Approved SABAS ALONSO
Final 4/24/2023 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/24/2023 SGSOV Approved SABAS ALONSO
Final 7/12/2023 OK to Issue CofO SABAS ALONSO