2231 S BALSAM AVE 90064

Certificate Information: 2231 S BALSAM AVE 90064

Application / Permit
21010-10000-00892
Plan Check / Job No.
B21LA03208
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 MAHNAZ NOURHASHEMI
Corrections Issued 3/25/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 3/28/2021 HERNAN ARREOLA
Applicant returned to address corrections 9/14/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 10/26/2021 MAHNAZ NOURHASHEMI
Issued 12/1/2021 APPLICANT
Building Plans Picked Up 12/6/2021 APPLICANT
CofO in Progress 2/15/2023 STEPHANIE SWANSON
Permit Finaled 2/16/2023 DANIEL ORRANTE
CofO Issued 2/16/2023 DANIEL ORRANTE
Permit Finaled 2/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 4/27/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 4/29/2021 ANTHONY MAINEZ
Sewer availability Cleared 4/29/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 5/19/2021 BRIAN MILLER
Hydrant and Access approval Cleared 6/4/2021 MATTHEW CRAIG
Specific Plan Cleared 7/26/2021 KEVIN ARUCAN
Low Impact Development Cleared 9/2/2021 SARAH YOUSSEF
Flood clearance Cleared 9/22/2021 TIFFANY WONG
Roof/Waste drainage to street Cleared 9/22/2021 ANTHONY MAINEZ
GPI Written Notices Cleared 9/29/2021 MAHNAZ NOURHASHEMI
Trees in Parkway Cleared 10/14/2021 MAHNAZ NOURHASHEMI

Contact Information

Architect Davis,, Scott John; Lic. No.: C35902 5233 HERSHOLT AVENUE      LAKEWOOD, CA 90712
Contractor Highground Builders; Lic. No.: 1042579-B 142 GLENDALE BLVD      LOS ANGELES, CA 90026
Engineer Chen,, Emily Hsiao Han; Lic. No.: C73319 22629 LAKESIDE LN      LAKE FOREST, CA 926303035

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/3/2021 Partial Approval BRENDAN LOONEY
FLOOD-Elevation Certificate 12/3/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 12/3/2021 Corrections Issued BRENDAN LOONEY
METHANE-Barrier 12/3/2021 Not Ready for Inspection BRENDAN LOONEY
METHANE-Subgrade 12/3/2021 Not Ready for Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/10/2021 Partial Approval BRENDAN LOONEY
FLOOD-Elevation Certificate 12/10/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 12/10/2021 Partial Approval BRENDAN LOONEY
METHANE-Barrier 12/10/2021 Not Ready for Inspection BRENDAN LOONEY
METHANE-Subgrade 12/10/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Methane Barrier 12/14/2021 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 12/21/2021 Partial Approval BRENDAN LOONEY
FLOOD-Elevation Certificate 12/21/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 12/21/2021 Conditional Approval BRENDAN LOONEY
METHANE-Barrier 12/21/2021 Conditional Approval BRENDAN LOONEY
METHANE-Rough 12/21/2021 Not Ready for Inspection BRENDAN LOONEY
METHANE-Subgrade 12/21/2021 Conditional Approval BRENDAN LOONEY
Deputy Methane Barrier 12/22/2021 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 1/11/2022 Not Ready for Inspection BRENDAN LOONEY
FLOOD-Proofing Certificate 1/11/2022 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 1/11/2022 Not Ready for Inspection BRENDAN LOONEY
METHANE-Rough 1/11/2022 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 1/11/2022 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 1/11/2022 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 1/14/2022 Partial Approval BRENDAN LOONEY
Wood Frame 1/20/2022 Conditional Approval BRENDAN LOONEY
Wood Frame 1/28/2022 Partial Approval BRENDAN LOONEY
Wood Frame 2/1/2022 Corrections Issued BRENDAN LOONEY
Special/Order Compliance 2/22/2022 Approved BRENDAN LOONEY
Special/Order Compliance 2/22/2022 Partial Inspection MICHAEL PELHAM
Pre-Inspection 3/9/2022 Partial Inspection BRENDAN LOONEY
Deputy Methane Barrier 3/15/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 3/16/2022 Partial Approval BRENDAN LOONEY
Deputy Methane Barrier 3/17/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 3/31/2022 Not Ready for Inspection BRENDAN LOONEY
FLOOD-Proofing Certificate 3/31/2022 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Corrections Issued BRENDAN LOONEY
Green Building Rough 3/31/2022 Not Ready for Inspection BRENDAN LOONEY
METHANE-Final 3/31/2022 Not Ready for Inspection BRENDAN LOONEY
METHANE-Rough 3/31/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 3/31/2022 Partial Approval BRENDAN LOONEY
Sewer 3/31/2022 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 3/31/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 4/4/2022 Corrections Issued BRENDAN LOONEY
Wood Frame 4/4/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 4/12/2022 Partial Approval BRENDAN LOONEY
METHANE-Final 4/12/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 4/12/2022 Corrections Issued BRENDAN LOONEY
Sewer 4/12/2022 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 4/14/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 4/14/2022 Conditional Approval BRENDAN LOONEY
Green Building Rough 4/14/2022 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 4/14/2022 Corrections Issued BRENDAN LOONEY
METHANE-Rough 4/14/2022 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 4/14/2022 Corrections Issued BRENDAN LOONEY
Sewer 4/18/2022 Partial Approval BRENDAN LOONEY
Wood Frame 4/18/2022 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 4/25/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 4/25/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 4/25/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 4/25/2022 Partial Approval BRENDAN LOONEY
METHANE-Rough 4/25/2022 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 5/4/2022 Not Ready for Inspection MICHAEL PELHAM
METHANE-Rough 5/4/2022 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 5/9/2022 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 5/9/2022 Not Ready for Inspection BRENDAN LOONEY
Insulation 5/9/2022 Corrections Issued BRENDAN LOONEY
METHANE-Final 5/9/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 5/9/2022 Partial Approval BRENDAN LOONEY
Shower Pan 5/9/2022 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 5/13/2022 Partial Approval BRENDAN LOONEY
Shower Pan 5/13/2022 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 5/18/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 5/18/2022 Approved BRENDAN LOONEY
HVAC-Rough 5/18/2022 Approved BRENDAN LOONEY
Insulation 5/18/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 5/18/2022 Approved BRENDAN LOONEY
METHANE-Rough 5/18/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 5/18/2022 Approved BRENDAN LOONEY
Sewer 5/18/2022 Approved BRENDAN LOONEY
Drywall Nailing 5/26/2022 Approved BRENDAN LOONEY
Gas Test 9/16/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 11/2/2022 Corrections Issued STEPHANIE SWANSON
Final 11/2/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Final 11/2/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 11/2/2022 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 1/12/2023 Approved STEPHANIE SWANSON
METHANE-Barrier 1/12/2023 Approved STEPHANIE SWANSON
METHANE-Subgrade 1/12/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 1/17/2023 Approved STEPHANIE SWANSON
Final 1/17/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 1/17/2023 Approved STEPHANIE SWANSON
HVAC-Final 1/17/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 1/17/2023 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Not Ready STEPHANIE SWANSON
Service/Power Release 1/17/2023 Not Ready for Inspection STEPHANIE SWANSON
Smoke Detectors 1/17/2023 Approved STEPHANIE SWANSON
Final 2/14/2023 Conditional Approval STEPHANIE SWANSON
HVAC-Final 2/14/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 2/14/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved STEPHANIE SWANSON
Service/Power Release 2/14/2023 Approved STEPHANIE SWANSON
Final 2/15/2023 OK to Issue CofO STEPHANIE SWANSON