3502-3502 1/2 E 7TH ST 90023

Certificate Information: 3502-3502 1/2 E 7TH ST 90023

Application / Permit
21010-10000-00862
Plan Check / Job No.
B21LA03089
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 38' X 38' (ZC: 2859 SF) 3 STORY DUPLEX WITH ATTACHED 4-CAR GARAGE (1068 SF) AT FRONT. (1 OF 3)
Permit Issued
Issued on 5/17/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/22/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 VIVIAN LAO
Corrections Issued 3/18/2021 VIVIAN LAO
Quality Review Completed 3/26/2021 MICHAEL PEREZ
Building Plans Picked Up 3/30/2021 APPLICANT
Plan Check Approved 11/15/2021 VIVIAN LAO
Issued 5/17/2022 APPLICANT
CofO in Progress 4/23/2024 FREDDIE RIVERA
Permit Finaled 4/24/2024 DEROLD HAUFF
CofO Issued 4/24/2024 DEROLD HAUFF
Permit Finaled 4/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/25/2021 JEANIE LAM
Permit Cleared 3/25/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/30/2021 JEANIE LAM
Sewer availability Cleared 3/30/2021 JEANIE LAM
Trees in Parkway Cleared 4/29/2021 JOHN KIM
Hydrant and Access approval Cleared 6/3/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/20/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/29/2021 JEANIE LAM

Contact Information

Contractor Builder Point Construction; Lic. No.: 1059885-B 11445 PARAMOUNT BLVD SUITE H      DOWNEY, CA 90241

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/3/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 1/9/2023 Partial Inspection FREDDIE RIVERA
Underground Mechanical 1/17/2023 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 1/27/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 5/25/2023 Corrections Issued FREDDIE RIVERA
HVAC-Rough 6/8/2023 Approved FREDDIE RIVERA
ELECTRICAL-Rough 6/9/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/15/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Approved FREDDIE RIVERA
Green Building Rough 6/15/2023 Approved FREDDIE RIVERA
MERV13>=Rough 6/15/2023 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 6/15/2023 Approved FREDDIE RIVERA
Wood Frame 6/15/2023 Partial Inspection FREDDIE RIVERA
Insulation 6/23/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/23/2023 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 6/28/2023 Corrections Issued FREDDIE RIVERA
Drywall Nailing 7/3/2023 Conditional Approval FREDDIE RIVERA
Interior/Exterior Lathing 7/12/2023 Partial Approval FREDDIE RIVERA
Gas Test 12/12/2023 Approved FREDDIE RIVERA
Verify Rec and Parks Fee Memo 12/12/2023 Partial Inspection FREDDIE RIVERA
HVAC-Final 2/8/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 2/8/2024 Corrections Issued FREDDIE RIVERA
HVAC-Final 2/26/2024 Approved FREDDIE RIVERA
PLUMBING-Final 2/26/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 2/29/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 3/8/2024 Partial Inspection FREDDIE RIVERA
Service/Power Release 3/8/2024 Partial Inspection FREDDIE RIVERA
Drywall Nailing 3/22/2024 Approved FREDDIE RIVERA
Final 3/22/2024 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 3/22/2024 Approved FREDDIE RIVERA
Green Building Final 3/22/2024 Approved FREDDIE RIVERA
MERV13>=Final 3/22/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved FREDDIE RIVERA
Service/Power Release 3/22/2024 Partial Inspection FREDDIE RIVERA
Smoke Detectors 3/22/2024 Approved FREDDIE RIVERA
Final 4/3/2024 Conditional Approval FREDDIE RIVERA
Service/Power Release 4/3/2024 Approved FREDDIE RIVERA
Final 4/18/2024 Conditional Approval FREDDIE RIVERA
Final 4/23/2024 OK to Issue CofO FREDDIE RIVERA