1765 N CAMPUS ROAD 90041
Certificate Information: 1765 N CAMPUS ROAD 90041
- Application / Permit
- 21010-10000-00854
- Plan Check / Job No.
- B21LA03071
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ACCESSORY DWELLING UNIT PER ORDINANCE LAMC 12.22a.33(b)(1)
- Permit Issued
- Issued on 9/16/2021
- Issuing Office
- Current Status
- CofO Issued on 3/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | VU NGUYEN |
| Corrections Issued | 3/9/2021 | VU NGUYEN |
| Applicant returned to address corrections | 8/27/2021 | VU NGUYEN |
| Plan Check Approved | 8/31/2021 | VU NGUYEN |
| Issued | 9/16/2021 | APPLICANT |
| Building Plans Picked Up | 9/17/2021 | APPLICANT |
| CofO in Progress | 3/16/2023 | CRAIG VAUGHAN |
| CofO Issued | 3/22/2023 | DEROLD HAUFF |
| Permit Finaled | 3/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 3/6/2021 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 3/6/2021 | VU NGUYEN |
| Address approval | Cleared | 4/14/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | THOMAS LANG |
| Sewer availability | Cleared | 4/15/2021 | THOMAS LANG |
| Low Impact Development | Cleared | 7/22/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/23/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/15/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/28/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 10/28/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 10/28/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 10/28/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Insulation | 11/1/2021 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/11/2022 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 2/11/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 2/11/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 2/11/2022 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 2/11/2022 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 2/11/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/4/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 3/8/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 3/8/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 3/15/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/15/2022 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/8/2022 | Partial Approval | SCOTT FINNILA |
| Shower Pan | 4/8/2022 | Approved | SCOTT FINNILA |
| Sewer | 5/23/2022 | Approved | ADAM ESCOTO |
| Gas Test | 5/26/2022 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/26/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 5/26/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/19/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 8/19/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 8/19/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 8/19/2022 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 8/19/2022 | Approved | CRAIG VAUGHAN |
| Gas Test | 8/31/2022 | Approved | BRIAN SULLIVAN |
| Final | 9/1/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 9/1/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 3/10/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 3/10/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/15/2023 | Approved | CRAIG VAUGHAN |
| Final | 3/15/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 3/15/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 3/15/2023 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 3/15/2023 | Approved | CRAIG VAUGHAN |