3429 E PERCY ST UNIT A 90023

Certificate Information: 3429 E PERCY ST UNIT A 90023

Application / Permit
21010-10000-00829
Plan Check / Job No.
B21LA03005
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU Addition. 1 STORY PROPOSED ADU PER CA GOVT CODE 65852.2(e)(1) (D) AND APPLICABLE PARTS OF LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 4/1/2022
Issuing Office
Current Status
CofO Corrected on 4/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 CRYSTEL MAALOUF
Corrections Issued 3/25/2021 CRYSTEL MAALOUF
Quality Review Completed 4/8/2021 WING SUEN
Applicant returned to address corrections 10/22/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 12/16/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 1/28/2022 CRYSTEL MAALOUF
Plan Check Approved 2/16/2022 CRYSTEL MAALOUF
Issued 4/1/2022 APPLICANT
CofO in Progress 2/22/2023 FREDDIE RIVERA
CofO Issued-Status Void 2/26/2023 DEROLD HAUFF
Permit Finaled-Status Void 2/26/2023 DEROLD HAUFF
Re-Activate Permit 4/27/2023 DEROLD HAUFF
Permit Finaled 4/27/2023 DEROLD HAUFF
CofO Corrected 4/27/2023 DEROLD HAUFF
Permit Finaled 4/27/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/28/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/29/2021 CECILIO NAVARRO
Address approval Cleared 5/3/2021 CECILIO NAVARRO
Clean Up Green Up Cleared 5/10/2021 RUBEN VASQUEZ
Hydrant and Access approval Cleared 6/15/2021 ROBERT DUFF
Sewer availability Cleared 9/16/2021 CECILIO NAVARRO

Contact Information

Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B 345 W LORAINE ST #3      GLENDALE, CA 91202
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/12/2022 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/12/2022 Partial Inspection FREDDIE RIVERA
Piling/Pier/Caisson 5/12/2022 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/22/2022 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 7/18/2022 Approved FREDDIE RIVERA
Underground Mechanical 7/18/2022 Partial Approval FREDDIE RIVERA
ELECTRICAL-Final 8/9/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 8/9/2022 Partial Inspection FREDDIE RIVERA
HVAC-Final 8/9/2022 Partial Inspection FREDDIE RIVERA
HVAC-Rough 8/9/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 8/9/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 8/9/2022 Partial Inspection FREDDIE RIVERA
Underground Mechanical 8/9/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 8/15/2022 Approved FREDDIE RIVERA
HVAC-Final 8/15/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 8/15/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/6/2023 Approved FREDDIE RIVERA
Final 2/6/2023 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 2/6/2023 Approved FREDDIE RIVERA
Green Building Final 2/6/2023 Approved FREDDIE RIVERA
Green Building Rough 2/6/2023 Approved FREDDIE RIVERA
MERV13>=Final 2/6/2023 Approved FREDDIE RIVERA
MERV13>=Rough 2/6/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 2/6/2023 Approved FREDDIE RIVERA
Final 2/22/2023 OK to Issue CofO FREDDIE RIVERA